عملیات خاکی: حجم خاکبرداری و خاکریزی، منحنی حمل و قیمتگذاری (کانادا)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · پروژهٔ خیالی
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- کار در ERP
- 5 تکلیف، حدود 3 ساعت 15 دقیقه
چه کسی چه چیزی به چه کسی میدهد
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
به شما میرسد
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron Driveتکلیف 1
- Mass ordinates of Marlow Avenueتکلیف 3
- Order: silt out, Granular B inتکلیف 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesتکلیف 4
از شما میرود
- Cut and fill quantitiesتکلیف 1
- Borrow and waste quantitiesتکلیف 2
- Overhaul and surplusتکلیف 3
- Rate for haul to wasteتکلیف 4
- Change for unsuitable siltتکلیف 5
مسیر شما در پروژه
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
تکلیف 1 · 35 دقیقه
خاکبرداری و خاکریزی با میانگین سطح مقاطع
- خروجی شما
- Cut and fill volumes, items 02.01 and 02.02
- سند
- Ten cross-sections of Heron Drive
- در ERP
- Bill of Quantities
Quantities
تکلیف 2 · 35 دقیقه
تورم، انقباض و نوبتهای کامیون
- خروجی شما
- Borrow to bring in, and truck loads to take away
- سند
- Soil factors and the engineer's note on wet clay
- در ERP
- Bill of Quantities
Quantities
تکلیف 3 · 40 دقیقه
منحنی حمل، حمل آزاد و حمل اضافی
- خروجی شما
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- سند
- Mass ordinates of Marlow Avenue
- در ERP
- Bill of Quantities
Rate
تکلیف 4 · 45 دقیقه
از بهرهوری ماشینآلات تا نرخ واحد
- خروجی شما
- The unit rate for haul to waste
- سند
- Machine costs, fuel and cycle times
- در ERP
- Bill of Quantities
Change
تکلیف 5 · 40 دقیقه
مصالح نامناسب: تغییری برای قیمتگذاری
- خروجی شما
- The priced change for unsuitable silt
- سند
- Test pit sections and agreed rates
- در ERP
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
آبی چیزی است که تکلیف اضافه میکند؛ خاکستری از مرحلهٔ قبل آمده است.
بهطور خلاصه. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.