Course introduction · 3 min
Earthworks: cut and fill, mass haul and pricing (Canada)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Fictional project
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Work in the ERP
- 5 tasks, about 3 h 15 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveTask 1
- Mass ordinates of Marlow AvenueTask 3
- Order: silt out, Granular B inTask 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesTask 4
Goes from you
- Cut and fill quantitiesTask 1
- Borrow and waste quantitiesTask 2
- Overhaul and surplusTask 3
- Rate for haul to wasteTask 4
- Change for unsuitable siltTask 5
Your route through the job
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Task 1 · 35 min
Cut and fill by average end area
- You produce
- Cut and fill volumes, items 02.01 and 02.02
- Document
- Ten cross-sections of Heron Drive
- In the ERP
- Bill of Quantities
Quantities
Task 2 · 35 min
Swell, shrinkage and truck loads
- You produce
- Borrow to bring in, and truck loads to take away
- Document
- Soil factors and the engineer's note on wet clay
- In the ERP
- Bill of Quantities
Quantities
Task 3 · 40 min
Mass haul, free haul and overhaul
- You produce
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Document
- Mass ordinates of Marlow Avenue
- In the ERP
- Bill of Quantities
Rate
Task 4 · 45 min
Equipment productivity to a unit rate
- You produce
- The unit rate for haul to waste
- Document
- Machine costs, fuel and cycle times
- In the ERP
- Bill of Quantities
Change
Task 5 · 40 min
Unsuitable material: a change to price
- You produce
- The priced change for unsuitable silt
- Document
- Test pit sections and agreed rates
- In the ERP
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Blue is what the task adds; grey is carried over from before.
In short. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.