OpenConstruction Academy
Logga in / Registrera
SV

Introduktion till kursen · 3 min

Schakt och fyllning: volymer, masstransport och prissättning (Kanada)

Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Fiktivt projekt

You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.

Starta uppgift 1

Work
Cut, fill, borrow (soil brought in) and haul for two streets
Contract
Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
Story
Tender in October 2026 to a change in June 2027
Arbete i ERP
5 uppgifter, cirka 3 h 15 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • The Town's engineerIssues sections, checks quantities
    • Cross-sections of Heron DriveUppgift 1
    • Mass ordinates of Marlow AvenueUppgift 3
    • Order: silt out, Granular B inUppgift 5
  • Site superintendentRuns the machines and trucks
    • Excavator, trucks and cycle timesUppgift 4
DuEstimator, earthworks contractor

Går från dig

    • Cut and fill quantitiesUppgift 1
    • Borrow and waste quantitiesUppgift 2
    • Overhaul and surplusUppgift 3
    • Rate for haul to wasteUppgift 4
    • Change for unsuitable siltUppgift 5
    The TownOwner, pays by the unit

Din väg genom projektet

Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.

  1. Quantities

    Uppgift 1 · 35 min

    Schakt och fyllning med medelareametoden

    Du tar fram
    Cut and fill volumes, items 02.01 and 02.02
    Dokument
    Ten cross-sections of Heron Drive
    I ERP
    Bill of Quantities
  2. Quantities

    Uppgift 2 · 35 min

    Svällning, packning och lass

    Du tar fram
    Borrow to bring in, and truck loads to take away
    Dokument
    Soil factors and the engineer's note on wet clay
    I ERP
    Bill of Quantities
  3. Quantities

    Uppgift 3 · 40 min

    Masstransport, fri transport och övertransport

    Du tar fram
    Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
    Dokument
    Mass ordinates of Marlow Avenue
    I ERP
    Bill of Quantities
  4. Rate

    Uppgift 4 · 45 min

    Maskinproduktivitet till ett enhetspris

    Du tar fram
    The unit rate for haul to waste
    Dokument
    Machine costs, fuel and cycle times
    I ERP
    Bill of Quantities
  5. Change

    Uppgift 5 · 40 min

    Olämpliga massor: prissättning av en ändring

    Du tar fram
    The priced change for unsuitable silt
    Dokument
    Test pit sections and agreed rates
    I ERP
    Variations

How a cross-section becomes a price

Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.

Cut and fill
Uppgift 1Measured volumesThe areas at each end of a slice times its length give cut and fill, each in its own unit and item.
Borrow and wasteCut and fill
Uppgift 2Borrow and wasteCut and fill compared in one state of the soil. What is short is imported, what is unusable leaves by truck.
Overhaul and surplusBorrow and wasteCut and fill
Uppgift 3HaulDistance beyond the free haul is paid as overhaul. What is left at the end is surplus.
Haul to waste, pricedOverhaul and surplusBorrow and wasteCut and fill
Uppgift 4A rate built upMachine output, hourly cost and the dump's gate fee give a price per bank m³ (soil as it lies in the ground).
Change for siltThe priced bill
Uppgift 5A changeUnsuitable silt out, granular fill in, at agreed rates and without HST (sales tax).

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.