Schakt och fyllning: volymer, masstransport och prissättning (Kanada)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Fiktivt projekt
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Arbete i ERP
- 5 uppgifter, cirka 3 h 15 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveUppgift 1
- Mass ordinates of Marlow AvenueUppgift 3
- Order: silt out, Granular B inUppgift 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesUppgift 4
Går från dig
- Cut and fill quantitiesUppgift 1
- Borrow and waste quantitiesUppgift 2
- Overhaul and surplusUppgift 3
- Rate for haul to wasteUppgift 4
- Change for unsuitable siltUppgift 5
Din väg genom projektet
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Uppgift 1 · 35 min
Schakt och fyllning med medelareametoden
- Du tar fram
- Cut and fill volumes, items 02.01 and 02.02
- Dokument
- Ten cross-sections of Heron Drive
- I ERP
- Bill of Quantities
Quantities
Uppgift 2 · 35 min
Svällning, packning och lass
- Du tar fram
- Borrow to bring in, and truck loads to take away
- Dokument
- Soil factors and the engineer's note on wet clay
- I ERP
- Bill of Quantities
Quantities
Uppgift 3 · 40 min
Masstransport, fri transport och övertransport
- Du tar fram
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Dokument
- Mass ordinates of Marlow Avenue
- I ERP
- Bill of Quantities
Rate
Uppgift 4 · 45 min
Maskinproduktivitet till ett enhetspris
- Du tar fram
- The unit rate for haul to waste
- Dokument
- Machine costs, fuel and cycle times
- I ERP
- Bill of Quantities
Change
Uppgift 5 · 40 min
Olämpliga massor: prissättning av en ändring
- Du tar fram
- The priced change for unsuitable silt
- Dokument
- Test pit sections and agreed rates
- I ERP
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.