Introduksjon til kurset · 3 min
Masseflytting: skjærings- og fyllevolumer, massediagram og prissetting (Canada)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Fiktivt prosjekt
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Arbeid i ERP
- 5 oppgaver, omtrent 3 t 15 min
Hvem gir hva til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til deg
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveOppgave 1
- Mass ordinates of Marlow AvenueOppgave 3
- Order: silt out, Granular B inOppgave 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesOppgave 4
Går fra deg
- Cut and fill quantitiesOppgave 1
- Borrow and waste quantitiesOppgave 2
- Overhaul and surplusOppgave 3
- Rate for haul to wasteOppgave 4
- Change for unsuitable siltOppgave 5
Din vei gjennom prosjektet
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Oppgave 1 · 35 min
Skjæring og fylling med middelarealmetoden
- Du leverer
- Cut and fill volumes, items 02.01 and 02.02
- Dokument
- Ten cross-sections of Heron Drive
- I ERP
- Bill of Quantities
Quantities
Oppgave 2 · 35 min
Svelling, komprimering og lastebillass
- Du leverer
- Borrow to bring in, and truck loads to take away
- Dokument
- Soil factors and the engineer's note on wet clay
- I ERP
- Bill of Quantities
Quantities
Oppgave 3 · 40 min
Masseforflytning, fri transport og overtransport
- Du leverer
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Dokument
- Mass ordinates of Marlow Avenue
- I ERP
- Bill of Quantities
Rate
Oppgave 4 · 45 min
Utstyrsproduktivitet til enhetspris
- Du leverer
- The unit rate for haul to waste
- Dokument
- Machine costs, fuel and cycle times
- I ERP
- Bill of Quantities
Change
Oppgave 5 · 40 min
Uegnede masser: prising av endring
- Du leverer
- The priced change for unsuitable silt
- Dokument
- Test pit sections and agreed rates
- I ERP
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Blått er det oppgaven legger til; grått er overført fra før.
Kort sagt. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.