Jordarbejde: udgravnings- og indbygningsvolumener, massefordeling og prissætning (Canada)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Fiktivt projekt
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Arbejde i ERP
- 5 opgaver, cirka 3 t 15 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveOpgave 1
- Mass ordinates of Marlow AvenueOpgave 3
- Order: silt out, Granular B inOpgave 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesOpgave 4
Går fra dig
- Cut and fill quantitiesOpgave 1
- Borrow and waste quantitiesOpgave 2
- Overhaul and surplusOpgave 3
- Rate for haul to wasteOpgave 4
- Change for unsuitable siltOpgave 5
Din vej gennem sagen
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Opgave 1 · 35 min
Udgravning og indbygning ved middelarealmetoden
- Du leverer
- Cut and fill volumes, items 02.01 and 02.02
- Dokument
- Ten cross-sections of Heron Drive
- I ERP
- Bill of Quantities
Quantities
Opgave 2 · 35 min
Svulmning, komprimering og lastbillæs
- Du leverer
- Borrow to bring in, and truck loads to take away
- Dokument
- Soil factors and the engineer's note on wet clay
- I ERP
- Bill of Quantities
Quantities
Opgave 3 · 40 min
Massekurve, fri transport og overtransport
- Du leverer
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Dokument
- Mass ordinates of Marlow Avenue
- I ERP
- Bill of Quantities
Rate
Opgave 4 · 45 min
Materielproduktivitet til enhedspris
- Du leverer
- The unit rate for haul to waste
- Dokument
- Machine costs, fuel and cycle times
- I ERP
- Bill of Quantities
Change
Opgave 5 · 40 min
Uegnede materialer: en ændring i prisen
- Du leverer
- The priced change for unsuitable silt
- Dokument
- Test pit sections and agreed rates
- I ERP
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.