OpenConstruction Academy
Log ind / Tilmeld
DA

Introduktion til kurset · 3 min

Jordarbejde: udgravnings- og indbygningsvolumener, massefordeling og prissætning (Canada)

Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Fiktivt projekt

You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.

Start opgave 1

Work
Cut, fill, borrow (soil brought in) and haul for two streets
Contract
Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
Story
Tender in October 2026 to a change in June 2027
Arbejde i ERP
5 opgaver, cirka 3 t 15 min

Hvem giver hvad til hvem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer til dig

  • The Town's engineerIssues sections, checks quantities
    • Cross-sections of Heron DriveOpgave 1
    • Mass ordinates of Marlow AvenueOpgave 3
    • Order: silt out, Granular B inOpgave 5
  • Site superintendentRuns the machines and trucks
    • Excavator, trucks and cycle timesOpgave 4
DigEstimator, earthworks contractor

Går fra dig

    • Cut and fill quantitiesOpgave 1
    • Borrow and waste quantitiesOpgave 2
    • Overhaul and surplusOpgave 3
    • Rate for haul to wasteOpgave 4
    • Change for unsuitable siltOpgave 5
    The TownOwner, pays by the unit

Din vej gennem sagen

Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.

  1. Quantities

    Opgave 1 · 35 min

    Udgravning og indbygning ved middelarealmetoden

    Du leverer
    Cut and fill volumes, items 02.01 and 02.02
    Dokument
    Ten cross-sections of Heron Drive
    I ERP
    Bill of Quantities
  2. Quantities

    Opgave 2 · 35 min

    Svulmning, komprimering og lastbillæs

    Du leverer
    Borrow to bring in, and truck loads to take away
    Dokument
    Soil factors and the engineer's note on wet clay
    I ERP
    Bill of Quantities
  3. Quantities

    Opgave 3 · 40 min

    Massekurve, fri transport og overtransport

    Du leverer
    Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
    Dokument
    Mass ordinates of Marlow Avenue
    I ERP
    Bill of Quantities
  4. Rate

    Opgave 4 · 45 min

    Materielproduktivitet til enhedspris

    Du leverer
    The unit rate for haul to waste
    Dokument
    Machine costs, fuel and cycle times
    I ERP
    Bill of Quantities
  5. Change

    Opgave 5 · 40 min

    Uegnede materialer: en ændring i prisen

    Du leverer
    The priced change for unsuitable silt
    Dokument
    Test pit sections and agreed rates
    I ERP
    Variations

How a cross-section becomes a price

Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.

Cut and fill
Opgave 1Measured volumesThe areas at each end of a slice times its length give cut and fill, each in its own unit and item.
Borrow and wasteCut and fill
Opgave 2Borrow and wasteCut and fill compared in one state of the soil. What is short is imported, what is unusable leaves by truck.
Overhaul and surplusBorrow and wasteCut and fill
Opgave 3HaulDistance beyond the free haul is paid as overhaul. What is left at the end is surplus.
Haul to waste, pricedOverhaul and surplusBorrow and wasteCut and fill
Opgave 4A rate built upMachine output, hourly cost and the dump's gate fee give a price per bank m³ (soil as it lies in the ground).
Change for siltThe priced bill
Opgave 5A changeUnsuitable silt out, granular fill in, at agreed rates and without HST (sales tax).

Blå er det, opgaven tilføjer; grå er overført fra før.

Kort sagt. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.