Why metraj comes first
A public building in Türkiye is usually let under Law 4734 as a unit-price contract (birim fiyat). The contractor is paid the contract unit price times the quantity actually built. The metraj, the take-off of quantities from the drawings, is therefore the basis of the cost estimate, the bid and every progress payment (hakediş). A wrong quantity is paid wrongly every month until someone remeasures it.