OpenConstruction Academy
Кіру / Тіркелу
KK

1-тапсырма алдындағы теория · 10 мин

Metraj: measuring walls from the drawing

Жоспар бойынша қабырғаларды өлшеу: A-101

Курсқа кіріспе

Бұл дәрістен кейін сіз мынаны үйренесіз

  1. Measure a wall by its axis length times its net height, counting each corner once.
  2. Deduct only the openings the specification tells you to, and keep the list of what you deducted.
  3. Explain why the quantity, not the price, is where a unit-price contract is won or lost.
1 / 3

Why metraj comes first

A public building in Türkiye is usually let under Law 4734 as a unit-price contract (birim fiyat). The contractor is paid the contract unit price times the quantity actually built. The metraj, the take-off of quantities from the drawings, is therefore the basis of the cost estimate, the bid and every progress payment (hakediş). A wrong quantity is paid wrongly every month until someone remeasures it.

Мысал. The administration checks the metraj line by line against the drawing. A figure without a traceable dimension is not accepted.
2 / 3

Axis length times net height

Walls are measured along their axis, the centre line of the wall, so that the outer and inner faces average out and every corner is counted once. The height is the net wall height between slabs: storey height less the slab. Axis length × net height gives the gross area of the wall.

Мысал. A rectangle of 18.00 × 9.00 m on axis has a wall length of 2 × (18.00 + 9.00) = 54.00 m.
Axis length, 2 × (a + b)54.0 m
Net wall height2.8 m
Gross wall area, m²151.2
3 / 3

Which openings come out

Doors and windows are deducted from the wall area, but small openings are not: the labour around them costs about as much as the wall they replace. Where the threshold lies is set by the measurement rules of the job; this course's technical specification deducts nothing under 1.00 m². Deduct each opening at its structural size, list each one, and keep the list: it is what the administration's controller checks first.

Мысал. A ventilation opening of 0.60 × 0.60 m (0.36 m²) stays in the wall area; a window of 1.50 × 1.20 m (1.80 m²) comes out.

Measure the outer wall of a small block

A single-storey block, 18.00 × 9.00 m on axis. Measure the net area of its outer wall.

Масштабсыз
Есеп шарты
  • Axis dimensions 18.0 m × 9.0 m; net wall height 2.8 m.
  • Openings: four windows 1.5 m × 1.2 m, one door 1.0 m × 2.2 m, two vents 0.6 m × 0.6 m.
  • Specification: openings under 1.00 m² are not deducted.
54.0 m2.8 m
54.0 m2.8 m
3 қадамның 1-і

Gross wall area

Axis length times net height. What is the gross area in m²?

2 × (18.0 m + 9.0 m) × 2.8 m = 151.2 m².

3 қадамның 2-і

Openings deducted

Four windows and the door; the vents are under 1.00 m². What area is deducted?

4 × 1.5 m × 1.2 m + 1.0 m × 2.2 m = 9.4 m². The vents (0.36 m² each) stay.

54.0 m2.8 m? m²
54.0 m2.8 m141.80 m²
3 қадамның 3-і

Net wall area

Gross less the deductions. What is the net area?

151.2 − 9.4 = 141.8 m².

Қысқаша. Axis length × net height, less the openings the specification names, each listed. That is the quantity the price will multiply every month.

Өзіңізді тексеріңіз

3 сұрақтың 1-і

A wall is 12.00 m long on axis and 3.00 m high net. It has one window of 2.00 × 1.50 m and one opening of 0.80 × 0.80 m. Small openings under 1.00 m² are not deducted. What is the net area?

36.00 − 3.00 = 33.00 m².
3 сұрақтың 2-і

Why are walls measured on their axis?

  • The axis is the centre line, not a face.

  • Right.

  • Unit prices are per m² of wall; the measuring line is set by the rules of measurement.

3 сұрақтың 3-і

A 0.50 m² service hole is in a wall. The specification sets a 1.00 m² threshold. What do you do?

  • Below the threshold it stays in the wall area.

  • Right. The work around it costs about as much as the wall.

  • There is no half deduction.