Курсқа кіріспе · 3 мин

Өлшеу, барыс төлемдері және баға түзету (Түркия)

You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.

1-тапсырманы бастау

A two-storey brick building wrapped in blue scaffolding with a concrete stair at its corner, pallets of blocks and a blue tarpaulin on bare ground in front.Ойдан шығарылған жоба
Çınardere Ek Derslik BinasıClassroom annex · brick walls under scaffolding
Building
Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
Contract
Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
Currency
Turkish lira, with KDV (VAT) as a deduction base
ERP-дегі жұмыс
Тапсырмалар: 5, шамамен 2 сағ 45 мин

Кім кімге не береді

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сізге келеді

  • İlçe kaymakamlığıEmployer (idare), pays the hakediş
    • Drawing A-101 and the keşif summary (bill)1-тапсырма
    • Analysis prices for the approximate cost2-тапсырма
    • Index tables and weights from the contract3-тапсырма
    • Tax and deduction rates5-тапсырма
  • Work programmeSays which month each work was due
    • Programmed months for the formwork4-тапсырма
СізMetraj ve hakediş engineer, contractor

Сізден кетеді

    • Wall take-off from A-1011-тапсырма
    • Hakediş 1 progress3-тапсырма
    Control engineerCo-signs the quantities (kontrol mühendisi)
    • Completed keşif and approximate cost2-тапсырма
    • Hakediş 2 with price adjustment4-тапсырма
    • Deductions and the amount payable5-тапсырма
    İlçe kaymakamlığıReceives the hakediş

Жоба бойынша жолыңыз

Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.

  1. Quantities and cost

    1-тапсырма · 35 мин

    Жоспар бойынша қабырғаларды өлшеу: A-101

    Нәтиже
    Net area of two wall items from the axis lengths
    Құжат
    Drawing A-101 and its general notes
    ERP-де
    Take-off
  2. Quantities and cost

    2-тапсырма · 30 мин

    Смета және болжамды құн

    Нәтиже
    Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
    Құжат
    Keşif summary with analysis prices
    ERP-де
    Bill of Quantities
  3. Price adjustment

    3-тапсырма · 35 мин

    1-сертификат және сәуірдегі баға түзету

    Нәтиже
    Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
    Құжат
    Weights and monthly indices
    ERP-де
    Contracts
  4. Price adjustment

    4-тапсырма · 35 мин

    2-сертификат: кешіккен жұмыстағы баға түзету

    Нәтиже
    May price adjustment with late work at the right index
    Құжат
    Work programme and May indices
    ERP-де
    Contracts
  5. Payment

    5-тапсырма · 30 мин

    2-сертификат: ҚҚС, салықтар және шегерімдер

    Нәтиже
    Each deduction from its own base, and the amount payable
    Құжат
    Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
    ERP-де
    Contracts

From the drawing to the amount paid

Each step narrows or adds to one money figure. The question each time is which base the rule applies to.

Openings that are deductedNet wall area
1-тапсырмаMetraj: net wall areaLength on the axis (the wall's centre line) times the net height, less only the openings the specification says to deduct.
Contractor profit, not in itQuantities at analysis prices
2-тапсырмаKeşif and approximate costQuantities times analysis prices, without contractor's profit. The employer's own figure to compare your bid with.
Price adjustment FWork done at contract prices
3-тапсырмаPrice adjustment, Pn and FWeights times the ratio of each index to its base month give Pn. F applies to the work done in the month and covers the rise only.
Price adjustment FLate work, programmed month's PnOn-time work, this month's Pn
4-тапсырмаLate workWork programmed for April but done in May by the contractor's fault takes the lower of the two months' Pn, so delay earns nothing.
KDV, partly withheld by the employerWithheld: stopaj, stamp duty, securityPaid to the contractor
5-тапсырмаDeductionsEach deduction has its own base: some on work only, some on work plus F. What is left is the contractor's payment.

Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.

Қысқаша. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.