Course introduction · 3 min

Takeoff, progress payments and price adjustment (Turkey)

You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.

Start task 1

A two-storey brick building wrapped in blue scaffolding with a concrete stair at its corner, pallets of blocks and a blue tarpaulin on bare ground in front.Fictional project
Çınardere Ek Derslik BinasıClassroom annex · brick walls under scaffolding
Building
Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
Contract
Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
Currency
Turkish lira, with KDV (VAT) as a deduction base
Work in the ERP
5 tasks, about 2 h 45 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • İlçe kaymakamlığıEmployer (idare), pays the hakediş
    • Drawing A-101 and the keşif summary (bill)Task 1
    • Analysis prices for the approximate costTask 2
    • Index tables and weights from the contractTask 3
    • Tax and deduction ratesTask 5
  • Work programmeSays which month each work was due
    • Programmed months for the formworkTask 4
YouMetraj ve hakediş engineer, contractor

Goes from you

    • Wall take-off from A-101Task 1
    • Hakediş 1 progressTask 3
    Control engineerCo-signs the quantities (kontrol mühendisi)
    • Completed keşif and approximate costTask 2
    • Hakediş 2 with price adjustmentTask 4
    • Deductions and the amount payableTask 5
    İlçe kaymakamlığıReceives the hakediş

Your route through the job

Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.

  1. Quantities and cost

    Task 1 · 35 min

    Wall takeoff from the plan: A-101

    You produce
    Net area of two wall items from the axis lengths
    Document
    Drawing A-101 and its general notes
    In the ERP
    Take-off
  2. Quantities and cost

    Task 2 · 30 min

    Estimate and approximate cost

    You produce
    Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
    Document
    Keşif summary with analysis prices
    In the ERP
    Bill of Quantities
  3. Price adjustment

    Task 3 · 35 min

    Certificate 1 and April price adjustment

    You produce
    Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
    Document
    Weights and monthly indices
    In the ERP
    Contracts
  4. Price adjustment

    Task 4 · 35 min

    Certificate 2: price adjustment on late work

    You produce
    May price adjustment with late work at the right index
    Document
    Work programme and May indices
    In the ERP
    Contracts
  5. Payment

    Task 5 · 30 min

    Certificate 2: VAT, taxes and deductions

    You produce
    Each deduction from its own base, and the amount payable
    Document
    Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
    In the ERP
    Contracts

From the drawing to the amount paid

Each step narrows or adds to one money figure. The question each time is which base the rule applies to.

Openings that are deductedNet wall area
Task 1Metraj: net wall areaLength on the axis (the wall's centre line) times the net height, less only the openings the specification says to deduct.
Contractor profit, not in itQuantities at analysis prices
Task 2Keşif and approximate costQuantities times analysis prices, without contractor's profit. The employer's own figure to compare your bid with.
Price adjustment FWork done at contract prices
Task 3Price adjustment, Pn and FWeights times the ratio of each index to its base month give Pn. F applies to the work done in the month and covers the rise only.
Price adjustment FLate work, programmed month's PnOn-time work, this month's Pn
Task 4Late workWork programmed for April but done in May by the contractor's fault takes the lower of the two months' Pn, so delay earns nothing.
KDV, partly withheld by the employerWithheld: stopaj, stamp duty, securityPaid to the contractor
Task 5DeductionsEach deduction has its own base: some on work only, some on work plus F. What is left is the contractor's payment.

Blue is what the task adds; grey is carried over from before.

In short. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.