Course introduction · 3 min
Takeoff, progress payments and price adjustment (Turkey)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Fictional project- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- Work in the ERP
- 5 tasks, about 2 h 45 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Task 1
- Analysis prices for the approximate costTask 2
- Index tables and weights from the contractTask 3
- Tax and deduction ratesTask 5
- Work programmeSays which month each work was due
- Programmed months for the formworkTask 4
Goes from you
- Wall take-off from A-101Task 1
- Hakediş 1 progressTask 3
- Completed keşif and approximate costTask 2
- Hakediş 2 with price adjustmentTask 4
- Deductions and the amount payableTask 5
Your route through the job
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Task 1 · 35 min
Wall takeoff from the plan: A-101
- You produce
- Net area of two wall items from the axis lengths
- Document
- Drawing A-101 and its general notes
- In the ERP
- Take-off
Quantities and cost
Task 2 · 30 min
Estimate and approximate cost
- You produce
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Document
- Keşif summary with analysis prices
- In the ERP
- Bill of Quantities
Price adjustment
Task 3 · 35 min
Certificate 1 and April price adjustment
- You produce
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Document
- Weights and monthly indices
- In the ERP
- Contracts
Price adjustment
Task 4 · 35 min
Certificate 2: price adjustment on late work
- You produce
- May price adjustment with late work at the right index
- Document
- Work programme and May indices
- In the ERP
- Contracts
Payment
Task 5 · 30 min
Certificate 2: VAT, taxes and deductions
- You produce
- Each deduction from its own base, and the amount payable
- Document
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- In the ERP
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Blue is what the task adds; grey is carried over from before.
In short. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.