Inleiding tot de cursus · 3 min
Opmeting, voortgangsbetalingen en prijsherziening (Turkije)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Fictief project- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- Werk in de ERP
- 5 opdrachten, ongeveer 2 u 45 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Opdracht 1
- Analysis prices for the approximate costOpdracht 2
- Index tables and weights from the contractOpdracht 3
- Tax and deduction ratesOpdracht 5
- Work programmeSays which month each work was due
- Programmed months for the formworkOpdracht 4
Gaat van u uit
- Wall take-off from A-101Opdracht 1
- Hakediş 1 progressOpdracht 3
- Completed keşif and approximate costOpdracht 2
- Hakediş 2 with price adjustmentOpdracht 4
- Deductions and the amount payableOpdracht 5
Uw route door het project
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Opdracht 1 · 35 min
Wandopmeting op de plattegrond: A-101
- U levert
- Net area of two wall items from the axis lengths
- Document
- Drawing A-101 and its general notes
- In de ERP
- Take-off
Quantities and cost
Opdracht 2 · 30 min
Raming en geraamde kosten
- U levert
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Document
- Keşif summary with analysis prices
- In de ERP
- Bill of Quantities
Price adjustment
Opdracht 3 · 35 min
Certificaat 1 en prijsherziening april
- U levert
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Document
- Weights and monthly indices
- In de ERP
- Contracts
Price adjustment
Opdracht 4 · 35 min
Certificaat 2: prijsherziening op laat werk
- U levert
- May price adjustment with late work at the right index
- Document
- Work programme and May indices
- In de ERP
- Contracts
Payment
Opdracht 5 · 30 min
Certificaat 2: btw, belastingen en inhoudingen
- U levert
- Each deduction from its own base, and the amount payable
- Document
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- In de ERP
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.