Επιμέτρηση, πιστοποιήσεις προόδου και αναθεώρηση τιμών (Τουρκία)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Φανταστικό έργο- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- Εργασία στο ERP
- 5 εργασίες, περίπου 2 ώ. 45 λ.
Ποιος δίνει τι σε ποιον
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Έρχεται σε εσάς
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Εργασία 1
- Analysis prices for the approximate costΕργασία 2
- Index tables and weights from the contractΕργασία 3
- Tax and deduction ratesΕργασία 5
- Work programmeSays which month each work was due
- Programmed months for the formworkΕργασία 4
Φεύγει από εσάς
- Wall take-off from A-101Εργασία 1
- Hakediş 1 progressΕργασία 3
- Completed keşif and approximate costΕργασία 2
- Hakediş 2 with price adjustmentΕργασία 4
- Deductions and the amount payableΕργασία 5
Η διαδρομή σας στο έργο
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Εργασία 1 · 35 λ.
Επιμέτρηση τοίχων από το σχέδιο: A-101
- Παράγετε
- Net area of two wall items from the axis lengths
- Έγγραφο
- Drawing A-101 and its general notes
- Στο ERP
- Take-off
Quantities and cost
Εργασία 2 · 30 λ.
Προϋπολογισμός και yaklaşık maliyet
- Παράγετε
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Έγγραφο
- Keşif summary with analysis prices
- Στο ERP
- Bill of Quantities
Price adjustment
Εργασία 3 · 35 λ.
Πιστοποιητικό 1 και αναθεώρηση τιμών Απριλίου
- Παράγετε
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Έγγραφο
- Weights and monthly indices
- Στο ERP
- Contracts
Price adjustment
Εργασία 4 · 35 λ.
Πιστοποιητικό 2: αναθεώρηση τιμών σε εκπρόθεσμες εργασίες
- Παράγετε
- May price adjustment with late work at the right index
- Έγγραφο
- Work programme and May indices
- Στο ERP
- Contracts
Payment
Εργασία 5 · 30 λ.
Πιστοποιητικό 2: ΦΠΑ, φόροι και κρατήσεις
- Παράγετε
- Each deduction from its own base, and the amount payable
- Έγγραφο
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- Στο ERP
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Με μπλε ό,τι προσθέτει η εργασία· με γκρι ό,τι έρχεται από πριν.
Με λίγα λόγια. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.