Επιμέτρηση, πιστοποιήσεις προόδου και αναθεώρηση τιμών (Τουρκία)

You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.

Έναρξη εργασίας 1

A two-storey brick building wrapped in blue scaffolding with a concrete stair at its corner, pallets of blocks and a blue tarpaulin on bare ground in front.Φανταστικό έργο
Çınardere Ek Derslik BinasıClassroom annex · brick walls under scaffolding
Building
Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
Contract
Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
Currency
Turkish lira, with KDV (VAT) as a deduction base
Εργασία στο ERP
5 εργασίες, περίπου 2 ώ. 45 λ.

Ποιος δίνει τι σε ποιον

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Έρχεται σε εσάς

  • İlçe kaymakamlığıEmployer (idare), pays the hakediş
    • Drawing A-101 and the keşif summary (bill)Εργασία 1
    • Analysis prices for the approximate costΕργασία 2
    • Index tables and weights from the contractΕργασία 3
    • Tax and deduction ratesΕργασία 5
  • Work programmeSays which month each work was due
    • Programmed months for the formworkΕργασία 4
ΕσείςMetraj ve hakediş engineer, contractor

Φεύγει από εσάς

    • Wall take-off from A-101Εργασία 1
    • Hakediş 1 progressΕργασία 3
    Control engineerCo-signs the quantities (kontrol mühendisi)
    • Completed keşif and approximate costΕργασία 2
    • Hakediş 2 with price adjustmentΕργασία 4
    • Deductions and the amount payableΕργασία 5
    İlçe kaymakamlığıReceives the hakediş

Η διαδρομή σας στο έργο

Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.

  1. Quantities and cost

    Εργασία 1 · 35 λ.

    Επιμέτρηση τοίχων από το σχέδιο: A-101

    Παράγετε
    Net area of two wall items from the axis lengths
    Έγγραφο
    Drawing A-101 and its general notes
    Στο ERP
    Take-off
  2. Quantities and cost

    Εργασία 2 · 30 λ.

    Προϋπολογισμός και yaklaşık maliyet

    Παράγετε
    Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
    Έγγραφο
    Keşif summary with analysis prices
    Στο ERP
    Bill of Quantities
  3. Price adjustment

    Εργασία 3 · 35 λ.

    Πιστοποιητικό 1 και αναθεώρηση τιμών Απριλίου

    Παράγετε
    Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
    Έγγραφο
    Weights and monthly indices
    Στο ERP
    Contracts
  4. Price adjustment

    Εργασία 4 · 35 λ.

    Πιστοποιητικό 2: αναθεώρηση τιμών σε εκπρόθεσμες εργασίες

    Παράγετε
    May price adjustment with late work at the right index
    Έγγραφο
    Work programme and May indices
    Στο ERP
    Contracts
  5. Payment

    Εργασία 5 · 30 λ.

    Πιστοποιητικό 2: ΦΠΑ, φόροι και κρατήσεις

    Παράγετε
    Each deduction from its own base, and the amount payable
    Έγγραφο
    Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
    Στο ERP
    Contracts

From the drawing to the amount paid

Each step narrows or adds to one money figure. The question each time is which base the rule applies to.

Openings that are deductedNet wall area
Εργασία 1Metraj: net wall areaLength on the axis (the wall's centre line) times the net height, less only the openings the specification says to deduct.
Contractor profit, not in itQuantities at analysis prices
Εργασία 2Keşif and approximate costQuantities times analysis prices, without contractor's profit. The employer's own figure to compare your bid with.
Price adjustment FWork done at contract prices
Εργασία 3Price adjustment, Pn and FWeights times the ratio of each index to its base month give Pn. F applies to the work done in the month and covers the rise only.
Price adjustment FLate work, programmed month's PnOn-time work, this month's Pn
Εργασία 4Late workWork programmed for April but done in May by the contractor's fault takes the lower of the two months' Pn, so delay earns nothing.
KDV, partly withheld by the employerWithheld: stopaj, stamp duty, securityPaid to the contractor
Εργασία 5DeductionsEach deduction has its own base: some on work only, some on work plus F. What is left is the contractor's payment.

Με μπλε ό,τι προσθέτει η εργασία· με γκρι ό,τι έρχεται από πριν.

Με λίγα λόγια. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.