Хэмжээ авалт, явцын төлбөр ба үнийн залруулга (Турк)

You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.

1-р даалгаврыг эхлэх

A two-storey brick building wrapped in blue scaffolding with a concrete stair at its corner, pallets of blocks and a blue tarpaulin on bare ground in front.Зохиомол төсөл
Çınardere Ek Derslik BinasıClassroom annex · brick walls under scaffolding
Building
Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
Contract
Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
Currency
Turkish lira, with KDV (VAT) as a deduction base
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 2 цаг 45 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • İlçe kaymakamlığıEmployer (idare), pays the hakediş
    • Drawing A-101 and the keşif summary (bill)Даалгавар 1
    • Analysis prices for the approximate costДаалгавар 2
    • Index tables and weights from the contractДаалгавар 3
    • Tax and deduction ratesДаалгавар 5
  • Work programmeSays which month each work was due
    • Programmed months for the formworkДаалгавар 4
ТаMetraj ve hakediş engineer, contractor

Танаас гардаг

    • Wall take-off from A-101Даалгавар 1
    • Hakediş 1 progressДаалгавар 3
    Control engineerCo-signs the quantities (kontrol mühendisi)
    • Completed keşif and approximate costДаалгавар 2
    • Hakediş 2 with price adjustmentДаалгавар 4
    • Deductions and the amount payableДаалгавар 5
    İlçe kaymakamlığıReceives the hakediş

Төслөөр явах таны зам

Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.

  1. Quantities and cost

    Даалгавар 1 · 35 мин

    Зургаас ханын хэмжээ авалт: A-101

    Үр дүн
    Net area of two wall items from the axis lengths
    Баримт бичиг
    Drawing A-101 and its general notes
    ERP дээр
    Take-off
  2. Quantities and cost

    Даалгавар 2 · 30 мин

    Тооцоо ба ойролцоо өртөг

    Үр дүн
    Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
    Баримт бичиг
    Keşif summary with analysis prices
    ERP дээр
    Bill of Quantities
  3. Price adjustment

    Даалгавар 3 · 35 мин

    Гэрчилгээ 1 ба дөрөвдүгээр сарын үнийн залруулга

    Үр дүн
    Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
    Баримт бичиг
    Weights and monthly indices
    ERP дээр
    Contracts
  4. Price adjustment

    Даалгавар 4 · 35 мин

    Гэрчилгээ 2: хоцорсон ажлын үнийн залруулга

    Үр дүн
    May price adjustment with late work at the right index
    Баримт бичиг
    Work programme and May indices
    ERP дээр
    Contracts
  5. Payment

    Даалгавар 5 · 30 мин

    Гэрчилгээ 2: НӨАТ, татвар ба суутгал

    Үр дүн
    Each deduction from its own base, and the amount payable
    Баримт бичиг
    Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
    ERP дээр
    Contracts

From the drawing to the amount paid

Each step narrows or adds to one money figure. The question each time is which base the rule applies to.

Openings that are deductedNet wall area
Даалгавар 1Metraj: net wall areaLength on the axis (the wall's centre line) times the net height, less only the openings the specification says to deduct.
Contractor profit, not in itQuantities at analysis prices
Даалгавар 2Keşif and approximate costQuantities times analysis prices, without contractor's profit. The employer's own figure to compare your bid with.
Price adjustment FWork done at contract prices
Даалгавар 3Price adjustment, Pn and FWeights times the ratio of each index to its base month give Pn. F applies to the work done in the month and covers the rise only.
Price adjustment FLate work, programmed month's PnOn-time work, this month's Pn
Даалгавар 4Late workWork programmed for April but done in May by the contractor's fault takes the lower of the two months' Pn, so delay earns nothing.
KDV, partly withheld by the employerWithheld: stopaj, stamp duty, securityPaid to the contractor
Даалгавар 5DeductionsEach deduction has its own base: some on work only, some on work plus F. What is left is the contractor's payment.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.