Сургалтын танилцуулга · 3 мин
Хэмжээ авалт, явцын төлбөр ба үнийн залруулга (Турк)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Зохиомол төсөл- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- ERP дээрх ажил
- Даалгавар: 5, ойролцоогоор 2 цаг 45 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Даалгавар 1
- Analysis prices for the approximate costДаалгавар 2
- Index tables and weights from the contractДаалгавар 3
- Tax and deduction ratesДаалгавар 5
- Work programmeSays which month each work was due
- Programmed months for the formworkДаалгавар 4
Танаас гардаг
- Wall take-off from A-101Даалгавар 1
- Hakediş 1 progressДаалгавар 3
- Completed keşif and approximate costДаалгавар 2
- Hakediş 2 with price adjustmentДаалгавар 4
- Deductions and the amount payableДаалгавар 5
Төслөөр явах таны зам
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Даалгавар 1 · 35 мин
Зургаас ханын хэмжээ авалт: A-101
- Үр дүн
- Net area of two wall items from the axis lengths
- Баримт бичиг
- Drawing A-101 and its general notes
- ERP дээр
- Take-off
Quantities and cost
Даалгавар 2 · 30 мин
Тооцоо ба ойролцоо өртөг
- Үр дүн
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Баримт бичиг
- Keşif summary with analysis prices
- ERP дээр
- Bill of Quantities
Price adjustment
Даалгавар 3 · 35 мин
Гэрчилгээ 1 ба дөрөвдүгээр сарын үнийн залруулга
- Үр дүн
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Баримт бичиг
- Weights and monthly indices
- ERP дээр
- Contracts
Price adjustment
Даалгавар 4 · 35 мин
Гэрчилгээ 2: хоцорсон ажлын үнийн залруулга
- Үр дүн
- May price adjustment with late work at the right index
- Баримт бичиг
- Work programme and May indices
- ERP дээр
- Contracts
Payment
Даалгавар 5 · 30 мин
Гэрчилгээ 2: НӨАТ, татвар ба суутгал
- Үр дүн
- Each deduction from its own base, and the amount payable
- Баримт бичиг
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- ERP дээр
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.