Курска киришүү · 3 мүн
Өлчөө, прогресс боюнча төлөмдөр жана баанын түзөтүлүшү (Түркия)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Ойдон чыгарылган долбоор- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- ERPдеги иш
- Тапшырмалар: 5, болжол менен 2 саат 45 мүн
Ким кимге эмне берет
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)1-тапшырма
- Analysis prices for the approximate cost2-тапшырма
- Index tables and weights from the contract3-тапшырма
- Tax and deduction rates5-тапшырма
- Work programmeSays which month each work was due
- Programmed months for the formwork4-тапшырма
Сизден кетет
- Wall take-off from A-1011-тапшырма
- Hakediş 1 progress3-тапшырма
- Completed keşif and approximate cost2-тапшырма
- Hakediş 2 with price adjustment4-тапшырма
- Deductions and the amount payable5-тапшырма
Долбоор боюнча жолуңуз
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
1-тапшырма · 35 мүн
Пландан дубалдарды өлчөө: A-101
- Натыйжа
- Net area of two wall items from the axis lengths
- Документ
- Drawing A-101 and its general notes
- ERPде
- Take-off
Quantities and cost
2-тапшырма · 30 мүн
Смета жана болжолдуу нарк
- Натыйжа
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Документ
- Keşif summary with analysis prices
- ERPде
- Bill of Quantities
Price adjustment
3-тапшырма · 35 мүн
1-тастыктама жана апрелдеги баанын түзөтүлүшү
- Натыйжа
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Документ
- Weights and monthly indices
- ERPде
- Contracts
Price adjustment
4-тапшырма · 35 мүн
2-тастыктама: кечиккен жумуш боюнча баа түзөтүү
- Натыйжа
- May price adjustment with late work at the right index
- Документ
- Work programme and May indices
- ERPде
- Contracts
Payment
5-тапшырма · 30 мүн
2-тастыктама: КНС, салыктар жана чегерүүлөр
- Натыйжа
- Each deduction from its own base, and the amount payable
- Документ
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- ERPде
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.