Курска киришүү · 3 мүн

Өлчөө, прогресс боюнча төлөмдөр жана баанын түзөтүлүшү (Түркия)

You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.

1-тапшырманы баштоо

A two-storey brick building wrapped in blue scaffolding with a concrete stair at its corner, pallets of blocks and a blue tarpaulin on bare ground in front.Ойдон чыгарылган долбоор
Çınardere Ek Derslik BinasıClassroom annex · brick walls under scaffolding
Building
Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
Contract
Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
Currency
Turkish lira, with KDV (VAT) as a deduction base
ERPдеги иш
Тапшырмалар: 5, болжол менен 2 саат 45 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • İlçe kaymakamlığıEmployer (idare), pays the hakediş
    • Drawing A-101 and the keşif summary (bill)1-тапшырма
    • Analysis prices for the approximate cost2-тапшырма
    • Index tables and weights from the contract3-тапшырма
    • Tax and deduction rates5-тапшырма
  • Work programmeSays which month each work was due
    • Programmed months for the formwork4-тапшырма
СизMetraj ve hakediş engineer, contractor

Сизден кетет

    • Wall take-off from A-1011-тапшырма
    • Hakediş 1 progress3-тапшырма
    Control engineerCo-signs the quantities (kontrol mühendisi)
    • Completed keşif and approximate cost2-тапшырма
    • Hakediş 2 with price adjustment4-тапшырма
    • Deductions and the amount payable5-тапшырма
    İlçe kaymakamlığıReceives the hakediş

Долбоор боюнча жолуңуз

Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.

  1. Quantities and cost

    1-тапшырма · 35 мүн

    Пландан дубалдарды өлчөө: A-101

    Натыйжа
    Net area of two wall items from the axis lengths
    Документ
    Drawing A-101 and its general notes
    ERPде
    Take-off
  2. Quantities and cost

    2-тапшырма · 30 мүн

    Смета жана болжолдуу нарк

    Натыйжа
    Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
    Документ
    Keşif summary with analysis prices
    ERPде
    Bill of Quantities
  3. Price adjustment

    3-тапшырма · 35 мүн

    1-тастыктама жана апрелдеги баанын түзөтүлүшү

    Натыйжа
    Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
    Документ
    Weights and monthly indices
    ERPде
    Contracts
  4. Price adjustment

    4-тапшырма · 35 мүн

    2-тастыктама: кечиккен жумуш боюнча баа түзөтүү

    Натыйжа
    May price adjustment with late work at the right index
    Документ
    Work programme and May indices
    ERPде
    Contracts
  5. Payment

    5-тапшырма · 30 мүн

    2-тастыктама: КНС, салыктар жана чегерүүлөр

    Натыйжа
    Each deduction from its own base, and the amount payable
    Документ
    Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
    ERPде
    Contracts

From the drawing to the amount paid

Each step narrows or adds to one money figure. The question each time is which base the rule applies to.

Openings that are deductedNet wall area
1-тапшырмаMetraj: net wall areaLength on the axis (the wall's centre line) times the net height, less only the openings the specification says to deduct.
Contractor profit, not in itQuantities at analysis prices
2-тапшырмаKeşif and approximate costQuantities times analysis prices, without contractor's profit. The employer's own figure to compare your bid with.
Price adjustment FWork done at contract prices
3-тапшырмаPrice adjustment, Pn and FWeights times the ratio of each index to its base month give Pn. F applies to the work done in the month and covers the rise only.
Price adjustment FLate work, programmed month's PnOn-time work, this month's Pn
4-тапшырмаLate workWork programmed for April but done in May by the contractor's fault takes the lower of the two months' Pn, so delay earns nothing.
KDV, partly withheld by the employerWithheld: stopaj, stamp duty, securityPaid to the contractor
5-тапшырмаDeductionsEach deduction has its own base: some on work only, some on work plus F. What is left is the contractor's payment.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.