Introduksjon til kurset · 3 min
Mengdeuttak, delbetalinger og prisregulering (Tyrkia)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Fiktivt prosjekt- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- Arbeid i ERP
- 5 oppgaver, omtrent 2 t 45 min
Hvem gir hva til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til deg
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Oppgave 1
- Analysis prices for the approximate costOppgave 2
- Index tables and weights from the contractOppgave 3
- Tax and deduction ratesOppgave 5
- Work programmeSays which month each work was due
- Programmed months for the formworkOppgave 4
Går fra deg
- Wall take-off from A-101Oppgave 1
- Hakediş 1 progressOppgave 3
- Completed keşif and approximate costOppgave 2
- Hakediş 2 with price adjustmentOppgave 4
- Deductions and the amount payableOppgave 5
Din vei gjennom prosjektet
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Oppgave 1 · 35 min
Veggmengder fra tegningen: A-101
- Du leverer
- Net area of two wall items from the axis lengths
- Dokument
- Drawing A-101 and its general notes
- I ERP
- Take-off
Quantities and cost
Oppgave 2 · 30 min
Kostnadsoverslag og estimert kostnad
- Du leverer
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Dokument
- Keşif summary with analysis prices
- I ERP
- Bill of Quantities
Price adjustment
Oppgave 3 · 35 min
Attest 1 og prisregulering for april
- Du leverer
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Dokument
- Weights and monthly indices
- I ERP
- Contracts
Price adjustment
Oppgave 4 · 35 min
Attest 2: prisregulering på forsinket arbeid
- Du leverer
- May price adjustment with late work at the right index
- Dokument
- Work programme and May indices
- I ERP
- Contracts
Payment
Oppgave 5 · 30 min
Attest 2: mva, skatter og trekk
- Du leverer
- Each deduction from its own base, and the amount payable
- Dokument
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- I ERP
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Blått er det oppgaven legger til; grått er overført fra før.
Kort sagt. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.