Kursuse sissejuhatus · 3 min
Mahtude arvutus, vahemaksed ja hinnakorrigeerimine (Türgi)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Väljamõeldud projekt- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- Töö ERP-s
- Ülesandeid 5, umbes 2 h 45 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Ülesanne 1
- Analysis prices for the approximate costÜlesanne 2
- Index tables and weights from the contractÜlesanne 3
- Tax and deduction ratesÜlesanne 5
- Work programmeSays which month each work was due
- Programmed months for the formworkÜlesanne 4
Läheb sinult
- Wall take-off from A-101Ülesanne 1
- Hakediş 1 progressÜlesanne 3
- Completed keşif and approximate costÜlesanne 2
- Hakediş 2 with price adjustmentÜlesanne 4
- Deductions and the amount payableÜlesanne 5
Sinu tee läbi projekti
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Ülesanne 1 · 35 min
Seinte mahud plaanilt: A-101
- Sinu tulemus
- Net area of two wall items from the axis lengths
- Dokument
- Drawing A-101 and its general notes
- ERP-s
- Take-off
Quantities and cost
Ülesanne 2 · 30 min
Hinnang ja hinnanguline maksumus
- Sinu tulemus
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Dokument
- Keşif summary with analysis prices
- ERP-s
- Bill of Quantities
Price adjustment
Ülesanne 3 · 35 min
Tõend 1 ja aprilli hinnakorrigeerimine
- Sinu tulemus
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Dokument
- Weights and monthly indices
- ERP-s
- Contracts
Price adjustment
Ülesanne 4 · 35 min
Tõend 2: hinnakorrigeerimine hilinenud töö eest
- Sinu tulemus
- May price adjustment with late work at the right index
- Dokument
- Work programme and May indices
- ERP-s
- Contracts
Payment
Ülesanne 5 · 30 min
Tõend 2: käibemaks, maksud ja mahaarvamised
- Sinu tulemus
- Each deduction from its own base, and the amount payable
- Dokument
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- ERP-s
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.