معرفی دوره · 3 دقیقه
متره، صورتوضعیتهای پیشرفت و تعدیل قیمت (ترکیه)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
پروژهٔ خیالی- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- کار در ERP
- 5 تکلیف، حدود 2 ساعت 45 دقیقه
چه کسی چه چیزی به چه کسی میدهد
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
به شما میرسد
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)تکلیف 1
- Analysis prices for the approximate costتکلیف 2
- Index tables and weights from the contractتکلیف 3
- Tax and deduction ratesتکلیف 5
- Work programmeSays which month each work was due
- Programmed months for the formworkتکلیف 4
از شما میرود
- Wall take-off from A-101تکلیف 1
- Hakediş 1 progressتکلیف 3
- Completed keşif and approximate costتکلیف 2
- Hakediş 2 with price adjustmentتکلیف 4
- Deductions and the amount payableتکلیف 5
مسیر شما در پروژه
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
تکلیف 1 · 35 دقیقه
متره دیوارها از روی نقشه: A-101
- خروجی شما
- Net area of two wall items from the axis lengths
- سند
- Drawing A-101 and its general notes
- در ERP
- Take-off
Quantities and cost
تکلیف 2 · 30 دقیقه
برآورد و هزینه تقریبی
- خروجی شما
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- سند
- Keşif summary with analysis prices
- در ERP
- Bill of Quantities
Price adjustment
تکلیف 3 · 35 دقیقه
گواهی 1 و تعدیل قیمت آوریل
- خروجی شما
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- سند
- Weights and monthly indices
- در ERP
- Contracts
Price adjustment
تکلیف 4 · 35 دقیقه
گواهی 2: تعدیل قیمت کار با تأخیر
- خروجی شما
- May price adjustment with late work at the right index
- سند
- Work programme and May indices
- در ERP
- Contracts
Payment
تکلیف 5 · 30 دقیقه
گواهی 2: VAT، مالیاتها و کسورات
- خروجی شما
- Each deduction from its own base, and the amount payable
- سند
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- در ERP
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
آبی چیزی است که تکلیف اضافه میکند؛ خاکستری از مرحلهٔ قبل آمده است.
بهطور خلاصه. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.