کورس کا تعارف · 3 منٹ
پیمائش، پیش رفت ادائیگیاں اور قیمتوں کی ایڈجسٹمنٹ (ترکی)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
فرضی پراجیکٹ- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- ERP میں کام
- 5 ٹاسک، تقریباً 2 گھنٹے 45 منٹ
کون کس کو کیا دیتا ہے
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
آپ کے پاس آتا ہے
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)ٹاسک 1
- Analysis prices for the approximate costٹاسک 2
- Index tables and weights from the contractٹاسک 3
- Tax and deduction ratesٹاسک 5
- Work programmeSays which month each work was due
- Programmed months for the formworkٹاسک 4
آپ سے جاتا ہے
- Wall take-off from A-101ٹاسک 1
- Hakediş 1 progressٹاسک 3
- Completed keşif and approximate costٹاسک 2
- Hakediş 2 with price adjustmentٹاسک 4
- Deductions and the amount payableٹاسک 5
پراجیکٹ میں آپ کا راستہ
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
ٹاسک 1 · 35 منٹ
نقشے سے دیواروں کی پیمائش: A-101
- آپ کا نتیجہ
- Net area of two wall items from the axis lengths
- دستاویز
- Drawing A-101 and its general notes
- ERP میں
- Take-off
Quantities and cost
ٹاسک 2 · 30 منٹ
تخمینہ اور تخمینی لاگت
- آپ کا نتیجہ
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- دستاویز
- Keşif summary with analysis prices
- ERP میں
- Bill of Quantities
Price adjustment
ٹاسک 3 · 35 منٹ
سرٹیفکیٹ 1 اور اپریل کی قیمت ایڈجسٹمنٹ
- آپ کا نتیجہ
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- دستاویز
- Weights and monthly indices
- ERP میں
- Contracts
Price adjustment
ٹاسک 4 · 35 منٹ
سرٹیفکیٹ 2: تاخیر سے ہونے والے کام پر قیمت ایڈجسٹمنٹ
- آپ کا نتیجہ
- May price adjustment with late work at the right index
- دستاویز
- Work programme and May indices
- ERP میں
- Contracts
Payment
ٹاسک 5 · 30 منٹ
سرٹیفکیٹ 2: VAT، ٹیکس اور کٹوتیاں
- آپ کا نتیجہ
- Each deduction from its own base, and the amount payable
- دستاویز
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- ERP میں
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
نیلا وہ ہے جو ٹاسک شامل کرتا ہے؛ سرمئی پچھلے مرحلے سے آیا ہے۔
مختصراً. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.