টেকঅফ, অগ্রগতি পেমেন্ট ও মূল্য সমন্বয় (তুরস্ক)

You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.

কাজ 1 শুরু করুন

A two-storey brick building wrapped in blue scaffolding with a concrete stair at its corner, pallets of blocks and a blue tarpaulin on bare ground in front.কাল্পনিক প্রকল্প
Çınardere Ek Derslik BinasıClassroom annex · brick walls under scaffolding
Building
Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
Contract
Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
Currency
Turkish lira, with KDV (VAT) as a deduction base
ERP-তে কাজ
5টি কাজ, প্রায় 2 ঘ 45 মি

কে কাকে কী দেয়

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

আপনার কাছে আসে

  • İlçe kaymakamlığıEmployer (idare), pays the hakediş
    • Drawing A-101 and the keşif summary (bill)কাজ 1
    • Analysis prices for the approximate costকাজ 2
    • Index tables and weights from the contractকাজ 3
    • Tax and deduction ratesকাজ 5
  • Work programmeSays which month each work was due
    • Programmed months for the formworkকাজ 4
আপনিMetraj ve hakediş engineer, contractor

আপনার কাছ থেকে যায়

    • Wall take-off from A-101কাজ 1
    • Hakediş 1 progressকাজ 3
    Control engineerCo-signs the quantities (kontrol mühendisi)
    • Completed keşif and approximate costকাজ 2
    • Hakediş 2 with price adjustmentকাজ 4
    • Deductions and the amount payableকাজ 5
    İlçe kaymakamlığıReceives the hakediş

প্রকল্পে আপনার পথ

Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.

  1. Quantities and cost

    কাজ 1 · 35 মি

    নকশা থেকে দেয়ালের টেকঅফ: A-101

    আপনার ফল
    Net area of two wall items from the axis lengths
    নথি
    Drawing A-101 and its general notes
    ERP-তে
    Take-off
  2. Quantities and cost

    কাজ 2 · 30 মি

    প্রাক্কলন ও আনুমানিক ব্যয়

    আপনার ফল
    Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
    নথি
    Keşif summary with analysis prices
    ERP-তে
    Bill of Quantities
  3. Price adjustment

    কাজ 3 · 35 মি

    সনদ 1 ও এপ্রিলের মূল্য সমন্বয়

    আপনার ফল
    Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
    নথি
    Weights and monthly indices
    ERP-তে
    Contracts
  4. Price adjustment

    কাজ 4 · 35 মি

    সনদ 2: দেরিতে হওয়া কাজে মূল্য সমন্বয়

    আপনার ফল
    May price adjustment with late work at the right index
    নথি
    Work programme and May indices
    ERP-তে
    Contracts
  5. Payment

    কাজ 5 · 30 মি

    সনদ 2: ভ্যাট, কর ও কর্তন

    আপনার ফল
    Each deduction from its own base, and the amount payable
    নথি
    Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
    ERP-তে
    Contracts

From the drawing to the amount paid

Each step narrows or adds to one money figure. The question each time is which base the rule applies to.

Openings that are deductedNet wall area
কাজ 1Metraj: net wall areaLength on the axis (the wall's centre line) times the net height, less only the openings the specification says to deduct.
Contractor profit, not in itQuantities at analysis prices
কাজ 2Keşif and approximate costQuantities times analysis prices, without contractor's profit. The employer's own figure to compare your bid with.
Price adjustment FWork done at contract prices
কাজ 3Price adjustment, Pn and FWeights times the ratio of each index to its base month give Pn. F applies to the work done in the month and covers the rise only.
Price adjustment FLate work, programmed month's PnOn-time work, this month's Pn
কাজ 4Late workWork programmed for April but done in May by the contractor's fault takes the lower of the two months' Pn, so delay earns nothing.
KDV, partly withheld by the employerWithheld: stopaj, stamp duty, securityPaid to the contractor
কাজ 5DeductionsEach deduction has its own base: some on work only, some on work plus F. What is left is the contractor's payment.

নীল হলো কাজটি যা যোগ করে; ধূসর আগের ধাপ থেকে আসা।

সংক্ষেপে. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.