টেকঅফ, অগ্রগতি পেমেন্ট ও মূল্য সমন্বয় (তুরস্ক)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
কাল্পনিক প্রকল্প- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- ERP-তে কাজ
- 5টি কাজ, প্রায় 2 ঘ 45 মি
কে কাকে কী দেয়
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
আপনার কাছে আসে
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)কাজ 1
- Analysis prices for the approximate costকাজ 2
- Index tables and weights from the contractকাজ 3
- Tax and deduction ratesকাজ 5
- Work programmeSays which month each work was due
- Programmed months for the formworkকাজ 4
আপনার কাছ থেকে যায়
- Wall take-off from A-101কাজ 1
- Hakediş 1 progressকাজ 3
- Completed keşif and approximate costকাজ 2
- Hakediş 2 with price adjustmentকাজ 4
- Deductions and the amount payableকাজ 5
প্রকল্পে আপনার পথ
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
কাজ 1 · 35 মি
নকশা থেকে দেয়ালের টেকঅফ: A-101
- আপনার ফল
- Net area of two wall items from the axis lengths
- নথি
- Drawing A-101 and its general notes
- ERP-তে
- Take-off
Quantities and cost
কাজ 2 · 30 মি
প্রাক্কলন ও আনুমানিক ব্যয়
- আপনার ফল
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- নথি
- Keşif summary with analysis prices
- ERP-তে
- Bill of Quantities
Price adjustment
কাজ 3 · 35 মি
সনদ 1 ও এপ্রিলের মূল্য সমন্বয়
- আপনার ফল
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- নথি
- Weights and monthly indices
- ERP-তে
- Contracts
Price adjustment
কাজ 4 · 35 মি
সনদ 2: দেরিতে হওয়া কাজে মূল্য সমন্বয়
- আপনার ফল
- May price adjustment with late work at the right index
- নথি
- Work programme and May indices
- ERP-তে
- Contracts
Payment
কাজ 5 · 30 মি
সনদ 2: ভ্যাট, কর ও কর্তন
- আপনার ফল
- Each deduction from its own base, and the amount payable
- নথি
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- ERP-তে
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
নীল হলো কাজটি যা যোগ করে; ধূসর আগের ধাপ থেকে আসা।
সংক্ষেপে. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.