Uvod u tečaj · 3 min

Iskaz količina, privremene situacije i revizija cijena (Turska)

You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.

Započni zadatak 1

A two-storey brick building wrapped in blue scaffolding with a concrete stair at its corner, pallets of blocks and a blue tarpaulin on bare ground in front.Izmišljeni projekt
Çınardere Ek Derslik BinasıClassroom annex · brick walls under scaffolding
Building
Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
Contract
Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
Currency
Turkish lira, with KDV (VAT) as a deduction base
Rad u ERP-u
Zadataka: 5, oko 2 h 45 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • İlçe kaymakamlığıEmployer (idare), pays the hakediş
    • Drawing A-101 and the keşif summary (bill)Zadatak 1
    • Analysis prices for the approximate costZadatak 2
    • Index tables and weights from the contractZadatak 3
    • Tax and deduction ratesZadatak 5
  • Work programmeSays which month each work was due
    • Programmed months for the formworkZadatak 4
ViMetraj ve hakediş engineer, contractor

Odlazi od vas

    • Wall take-off from A-101Zadatak 1
    • Hakediş 1 progressZadatak 3
    Control engineerCo-signs the quantities (kontrol mühendisi)
    • Completed keşif and approximate costZadatak 2
    • Hakediş 2 with price adjustmentZadatak 4
    • Deductions and the amount payableZadatak 5
    İlçe kaymakamlığıReceives the hakediş

Vaš put kroz projekt

Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.

  1. Quantities and cost

    Zadatak 1 · 35 min

    Iskaz količina zidova iz nacrta: A-101

    Vaš rezultat
    Net area of two wall items from the axis lengths
    Dokument
    Drawing A-101 and its general notes
    U ERP-u
    Take-off
  2. Quantities and cost

    Zadatak 2 · 30 min

    Procjena i procijenjena vrijednost

    Vaš rezultat
    Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
    Dokument
    Keşif summary with analysis prices
    U ERP-u
    Bill of Quantities
  3. Price adjustment

    Zadatak 3 · 35 min

    Situacija 1 i travanjska revizija cijena

    Vaš rezultat
    Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
    Dokument
    Weights and monthly indices
    U ERP-u
    Contracts
  4. Price adjustment

    Zadatak 4 · 35 min

    Situacija 2: revizija cijena na zakašnjele radove

    Vaš rezultat
    May price adjustment with late work at the right index
    Dokument
    Work programme and May indices
    U ERP-u
    Contracts
  5. Payment

    Zadatak 5 · 30 min

    Situacija 2: PDV, porezi i odbici

    Vaš rezultat
    Each deduction from its own base, and the amount payable
    Dokument
    Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
    U ERP-u
    Contracts

From the drawing to the amount paid

Each step narrows or adds to one money figure. The question each time is which base the rule applies to.

Openings that are deductedNet wall area
Zadatak 1Metraj: net wall areaLength on the axis (the wall's centre line) times the net height, less only the openings the specification says to deduct.
Contractor profit, not in itQuantities at analysis prices
Zadatak 2Keşif and approximate costQuantities times analysis prices, without contractor's profit. The employer's own figure to compare your bid with.
Price adjustment FWork done at contract prices
Zadatak 3Price adjustment, Pn and FWeights times the ratio of each index to its base month give Pn. F applies to the work done in the month and covers the rise only.
Price adjustment FLate work, programmed month's PnOn-time work, this month's Pn
Zadatak 4Late workWork programmed for April but done in May by the contractor's fault takes the lower of the two months' Pn, so delay earns nothing.
KDV, partly withheld by the employerWithheld: stopaj, stamp duty, securityPaid to the contractor
Zadatak 5DeductionsEach deduction has its own base: some on work only, some on work plus F. What is left is the contractor's payment.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.