Uvod u tečaj · 3 min
Iskaz količina, privremene situacije i revizija cijena (Turska)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Izmišljeni projekt- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- Rad u ERP-u
- Zadataka: 5, oko 2 h 45 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Zadatak 1
- Analysis prices for the approximate costZadatak 2
- Index tables and weights from the contractZadatak 3
- Tax and deduction ratesZadatak 5
- Work programmeSays which month each work was due
- Programmed months for the formworkZadatak 4
Odlazi od vas
- Wall take-off from A-101Zadatak 1
- Hakediş 1 progressZadatak 3
- Completed keşif and approximate costZadatak 2
- Hakediş 2 with price adjustmentZadatak 4
- Deductions and the amount payableZadatak 5
Vaš put kroz projekt
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Zadatak 1 · 35 min
Iskaz količina zidova iz nacrta: A-101
- Vaš rezultat
- Net area of two wall items from the axis lengths
- Dokument
- Drawing A-101 and its general notes
- U ERP-u
- Take-off
Quantities and cost
Zadatak 2 · 30 min
Procjena i procijenjena vrijednost
- Vaš rezultat
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Dokument
- Keşif summary with analysis prices
- U ERP-u
- Bill of Quantities
Price adjustment
Zadatak 3 · 35 min
Situacija 1 i travanjska revizija cijena
- Vaš rezultat
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Dokument
- Weights and monthly indices
- U ERP-u
- Contracts
Price adjustment
Zadatak 4 · 35 min
Situacija 2: revizija cijena na zakašnjele radove
- Vaš rezultat
- May price adjustment with late work at the right index
- Dokument
- Work programme and May indices
- U ERP-u
- Contracts
Payment
Zadatak 5 · 30 min
Situacija 2: PDV, porezi i odbici
- Vaš rezultat
- Each deduction from its own base, and the amount payable
- Dokument
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- U ERP-u
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.