Introducere în curs · 3 min
Antemăsurătoare, situații de plată și actualizarea prețurilor (Turcia)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Proiect fictiv- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- Lucru în ERP
- 5 sarcini, circa 2 h 45 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Sarcina 1
- Analysis prices for the approximate costSarcina 2
- Index tables and weights from the contractSarcina 3
- Tax and deduction ratesSarcina 5
- Work programmeSays which month each work was due
- Programmed months for the formworkSarcina 4
Pleacă de la tine
- Wall take-off from A-101Sarcina 1
- Hakediş 1 progressSarcina 3
- Completed keşif and approximate costSarcina 2
- Hakediş 2 with price adjustmentSarcina 4
- Deductions and the amount payableSarcina 5
Traseul tău prin proiect
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Sarcina 1 · 35 min
Antemăsurătoarea zidurilor din plan: A-101
- Produci
- Net area of two wall items from the axis lengths
- Document
- Drawing A-101 and its general notes
- În ERP
- Take-off
Quantities and cost
Sarcina 2 · 30 min
Deviz și cost aproximativ
- Produci
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Document
- Keşif summary with analysis prices
- În ERP
- Bill of Quantities
Price adjustment
Sarcina 3 · 35 min
Situația de plată 1 și actualizarea prețurilor din aprilie
- Produci
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Document
- Weights and monthly indices
- În ERP
- Contracts
Price adjustment
Sarcina 4 · 35 min
Situația de plată 2: actualizarea prețurilor la lucrările întârziate
- Produci
- May price adjustment with late work at the right index
- Document
- Work programme and May indices
- În ERP
- Contracts
Payment
Sarcina 5 · 30 min
Situația de plată 2: TVA, impozite și rețineri
- Produci
- Each deduction from its own base, and the amount payable
- Document
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- În ERP
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.