מבוא לקורס · 3 דק׳
כימות, חשבונות חלקיים והתאמת מחירים (טורקיה)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
פרויקט בדיוני- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- עבודה ב-ERP
- 5 משימות, כ-2 ש׳ 45 דק׳
מי מעביר מה למי
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
מגיע אליכם
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)משימה 1
- Analysis prices for the approximate costמשימה 2
- Index tables and weights from the contractמשימה 3
- Tax and deduction ratesמשימה 5
- Work programmeSays which month each work was due
- Programmed months for the formworkמשימה 4
יוצא מכם
- Wall take-off from A-101משימה 1
- Hakediş 1 progressמשימה 3
- Completed keşif and approximate costמשימה 2
- Hakediş 2 with price adjustmentמשימה 4
- Deductions and the amount payableמשימה 5
המסלול שלכם בפרויקט
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
משימה 1 · 35 דק׳
כימות קירות מהתוכנית: A-101
- התוצר שלכם
- Net area of two wall items from the axis lengths
- מסמך
- Drawing A-101 and its general notes
- ב-ERP
- Take-off
Quantities and cost
משימה 2 · 30 דק׳
אומדן ועלות משוערת
- התוצר שלכם
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- מסמך
- Keşif summary with analysis prices
- ב-ERP
- Bill of Quantities
Price adjustment
משימה 3 · 35 דק׳
אישור 1 והתאמת מחיר לאפריל
- התוצר שלכם
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- מסמך
- Weights and monthly indices
- ב-ERP
- Contracts
Price adjustment
משימה 4 · 35 דק׳
אישור 2: התאמת מחיר על עבודה מאוחרת
- התוצר שלכם
- May price adjustment with late work at the right index
- מסמך
- Work programme and May indices
- ב-ERP
- Contracts
Payment
משימה 5 · 30 דק׳
אישור 2: מע"מ, מסים וניכויים
- התוצר שלכם
- Each deduction from its own base, and the amount payable
- מסמך
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- ב-ERP
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
בכחול מה שהמשימה מוסיפה; באפור מה שעבר מהשלב הקודם.
בקצרה. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.