Въведение в курса · 3 мин
Измерване на количества, междинни плащания и ценова корекция (Турция)
You are the contractor's quantity and payment engineer (metraj ve hakediş mühendisi) on a four-classroom school annex in Türkiye: you measure what is built and claim payment for it. In five tasks you take off the walls from the drawing, complete the bill, send the monthly payment statement (hakediş) with its price adjustment (fiyat farkı, the extra paid when prices rise), and close it with the taxes and deductions.
Измислен проект- Building
- Single-storey annex with four classrooms, run by the district governorate (kaymakamlık)
- Contract
- Unit-price public works contract under Law 4734 (the Turkish public procurement law), with price adjustment (fiyat farkı)
- Currency
- Turkish lira, with KDV (VAT) as a deduction base
- Работа в ERP
- Задачи: 5, около 2 ч 45 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- İlçe kaymakamlığıEmployer (idare), pays the hakediş
- Drawing A-101 and the keşif summary (bill)Задача 1
- Analysis prices for the approximate costЗадача 2
- Index tables and weights from the contractЗадача 3
- Tax and deduction ratesЗадача 5
- Work programmeSays which month each work was due
- Programmed months for the formworkЗадача 4
Тръгва от вас
- Wall take-off from A-101Задача 1
- Hakediş 1 progressЗадача 3
- Completed keşif and approximate costЗадача 2
- Hakediş 2 with price adjustmentЗадача 4
- Deductions and the amount payableЗадача 5
Вашият път през проекта
Two tasks establish the quantities and the cost, three run a payment statement from the first month to the cash paid out. Start with task 1: in Take-off you measure the net area of two wall items from the axis lengths on drawing A-101.
Quantities and cost
Задача 1 · 35 мин
Измерване на стените по плана: A-101
- Вашият резултат
- Net area of two wall items from the axis lengths
- Документ
- Drawing A-101 and its general notes
- В ERP
- Take-off
Quantities and cost
Задача 2 · 30 мин
Разчет и прогнозна стойност
- Вашият резултат
- Complete keşif (the priced list of all work) and the approximate cost (yaklaşık maliyet, the employer's own estimate)
- Документ
- Keşif summary with analysis prices
- В ERP
- Bill of Quantities
Price adjustment
Задача 3 · 35 мин
Удостоверение 1 и ценова корекция за април
- Вашият резултат
- Hakediş 1 and the April price adjustment: Pn (the price-change factor), then F (the amount it adds)
- Документ
- Weights and monthly indices
- В ERP
- Contracts
Price adjustment
Задача 4 · 35 мин
Удостоверение 2: ценова корекция за закъсняла работа
- Вашият резултат
- May price adjustment with late work at the right index
- Документ
- Work programme and May indices
- В ERP
- Contracts
Payment
Задача 5 · 30 мин
Удостоверение 2: ДДС, данъци и удръжки
- Вашият резултат
- Each deduction from its own base, and the amount payable
- Документ
- Rates of KDV (VAT), stopaj (income tax withheld), damga (stamp duty), tevkifat (VAT withheld)
- В ERP
- Contracts
From the drawing to the amount paid
Each step narrows or adds to one money figure. The question each time is which base the rule applies to.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Measure on the axis. Price without profit for the approximate cost. Compare each month with the base. Late work never gets the higher index. Deduct each item from its own base.