Derive a plaster quantity from wall quantities: one face of outer walls, two faces of inner walls.
Price a keşif özeti from analysis unit prices that carry no profit and overheads.
Add the 25 % contractor's profit and general expenses to reach the approximate cost.
1 / 3
What the approximate cost is for
Before a public tender the administration calculates what the work should cost: the yaklaşık maliyet. It is the yardstick for the tender: it sets the threshold values and the bid bonds, and the administration compares bids against it. It is built from the keşif özeti, the list of items with quantities and unit prices, priced from public unit prices and analyses, not from any bidder's prices.
Мысал. A bidder's own unit prices are a bid, not a yardstick. Using them for the approximate cost makes the comparison circular.
2 / 3
Analysis prices plus 25 %
Unit prices from an analysis (analiz) are costs: labour, materials and plant, without the contractor's profit and general expenses and without KDV. The Public Works Tender Implementation Regulation (Yapım İşleri İhaleleri Uygulama Yönetmeliği, article 11) adds 25 % for contractor's profit and general expenses to such costs. The approximate cost is stated without KDV.
Мысал. Keşif total 160,347.60 at cost becomes 200,434.50 with 25 %.
Keşif total at analysis prices₺160,347.60
Profit and general expenses, 25 %₺40,086.90
Approximate cost, without KDV₺200,434.50
3 / 3
Derived quantities: plaster from walls
Many items are not measured again from the drawing but derived from items already measured. Internal plaster covers the inner face of the outer walls and both faces of the inner walls. Taking it from the net wall areas keeps the openings consistent: what was deducted from the wall is also missing from the plaster.
Мысал. Outer wall net 141.80 m², inner walls net 64.50 m²: plaster = 141.80 + 2 × 64.50 = 270.80 m².
Price a short keşif
Three items of a small block. Derive the plaster, total the keşif at analysis prices and find the approximate cost.
Масштабсыз
Есеп шарты
Outer wall net 141.8 m² at ₺640.00 per m² (analysis price, no profit, no KDV).
Inner walls net 64.5 m²; internal plaster at ₺185.00 per m²; paint on the same plastered area at ₺72.00 per m².
Profit and general expenses: 25 %.
3 қадамның 1-і
Internal plaster
Inner face of the outer wall plus both faces of the inner walls. How many m²?
Кеңес: Inner walls get plaster on both sides.
141.8 + 2 × 64.5 = 270.8 m².
₺90,752₺50,098
Walls ₺90,752
Plaster ₺50,098
Paint ₺19,498
₺90,752₺50,098
Walls ₺90,752
Plaster ₺50,098
Paint ₺19,498
3 қадамның 2-і
Keşif total at cost
Wall, plaster and paint, each quantity × unit price. What is the keşif total?
Add 25 % profit and general expenses. What is the approximate cost without KDV?
Кеңес: Keşif total × 1.25.
₺160,347.60 × 1.25 = ₺200,434.50.
Қысқаша. Derive quantities from measured ones, price them at analysis cost, add 25 %. The approximate cost is the administration's yardstick, built without any bidder's prices.
Өзіңізді тексеріңіз
3 сұрақтың 1-і
A keşif totals 84,000.00 at analysis prices without profit. What is the approximate cost without KDV?
84,000.00 × 1.25 = ₺105,000.00.
3 сұрақтың 2-і
Which prices build the approximate cost?
Bids are compared with the approximate cost, so they cannot form it.
Right.
The approximate cost is built item by item from the keşif.
3 сұрақтың 3-і
An inner wall is 20 m² net. How much internal plaster does it carry?