OpenConstruction Academy
Přihlásit se / Registrace
CS

Teorie před úlohou 4 · 10 min

The prompt payment calendar

Kalendář rychlé platby

Po této přednášce dokážete

  1. Count the Construction Act's deadlines from the day a proper invoice is received.
  2. Move a deadline that ends on a holiday the way the Legislation Act, 2006 says.
  3. Work out what a disputed part of a claim would have paid, holdback and HST applied.
1 / 3

Two clocks start on receipt

Under Ontario's Construction Act, s. 6.4, an owner must pay a proper invoice no later than 28 days after receiving it. If it disputes all or part, it must give a notice of non-payment, in the prescribed form, no later than 14 days after receipt, stating the amount not paid and every reason. Miss the notice deadline and the disputed amount is still due on day 28. The contractor in turn pays its subcontractors within seven days of being paid (s. 6.5).

Příklad. Receipt is day 0. The notice clock and the payment clock both run in calendar days from there.
2 / 3

A contract cannot give the owner longer

Section 5 (1) deems every contract amended to conform with the Act. A contract that gives the owner 45 days to pay is read as giving it 28. The contract can be stricter on the owner, not looser.

Příklad. Contract says 45 days: the owner still pays by day 28.
3 / 3

When a deadline lands on a holiday

The Legislation Act, 2006, s. 89 (1), extends a time limit that ends on a holiday to the next day that is not a holiday. Section 88 lists the holidays: every Sunday, New Year's Day, Good Friday, Easter Monday, Victoria Day, Canada Day, Labour Day, Thanksgiving, Christmas Day, Boxing Day and the others it names. Count first, then look at the day you land on; if it is a holiday, keep moving until it is not.

Příklad. Received Monday 13 September 2027. Day 28 is Monday 11 October, Thanksgiving, so payment is due Tuesday 12 October.

Dates and money for a disputed claim

A contractor's claim reached the owner as a proper invoice on Monday 13 September 2027. The owner disputes the mechanical division for the period and accepts the rest.

Není v měřítku
Zadání
  • Received Monday 13 September 2027. Thanksgiving is Monday 11 October 2027.
  • Disputed mechanical value for the period, excluding HST: $96,000.00.
  • Holdback 10%; HST 13% on the net paid.
Krok 1 z 2

Payment deadline

Count 28 days from 13 September; the day you land on is Thanksgiving. How many calendar days does the owner really have?

13 September + 28 days = Monday 11 October, Thanksgiving; the deadline moves to Tuesday 12 October, 29 days after receipt.

+$96,0001−$9,6002+$11,2323?4
  • 1 Disputed value
  • 2 Holdback
  • 3 HST on net
  • 4 Would be paid
+$96,0001−$9,6002+$11,2323$97,6324
  • 1 Disputed value
  • 2 Holdback
  • 3 HST on net
  • 4 Would be paid
Krok 2 z 2

Disputed amount as it would be paid

Take off holdback, add HST on the net. What would the disputed division have paid?

$96,000.00 × 0.90 × 1.13 = $97,632.00.

Stručně. Count from receipt, check where you land, move off holidays. The money in dispute is valued exactly as it would be paid.

Zkontrolujte se

Otázka 1 z 3

An owner disputes a division worth $72,000.00 excluding HST. Holdback is 10 %, HST 13 % on the net. What amount, HST included, is withheld from this payment?

$72,000.00 × 0.90 × 1.13 = $73,224.00.
Otázka 2 z 3

The contract gives the owner 45 days to pay a proper invoice. When must it pay?

  • Section 5 (1) deems the contract amended to conform with the Act.

  • Right. The statutory period governs.

  • That deadline is for the notice, not for payment.

Otázka 3 z 3

The last day for a notice of non-payment falls on a Sunday. The next day is an ordinary Monday. When is the notice late?

  • Deadlines move forward, never back.

  • Right. Sunday is a holiday, so the limit runs to Monday.

  • A limit ending on a holiday runs to the next day that is not one.