Two clocks start on receipt
Under Ontario's Construction Act, s. 6.4, an owner must pay a proper invoice no later than 28 days after receiving it. If it disputes all or part, it must give a notice of non-payment, in the prescribed form, no later than 14 days after receipt, stating the amount not paid and every reason. Miss the notice deadline and the disputed amount is still due on day 28. The contractor in turn pays its subcontractors within seven days of being paid (s. 6.5).