Progress payment: advance recovery and retention on the right base
Průběžná platba a zúčtování zálohy
Po této přednášce dokážete
Turn work done this period into its tax-inclusive value with VAT.
Recover the advance pro rata on the tax-inclusive value, as the contract says.
Withhold retention (质保金) on the value without VAT.
1 / 3
Two amounts kept back, two different bases
A progress payment (进度款) pays for work measured in the period. Two amounts come off it. The advance payment (预付款), paid at the start, is recovered in instalments; here the contract recovers it pro rata: 10 % of the tax-inclusive value of each period. Retention (质保金) is security for defects, held until the defects liability period ends; here it is 3 % of the value without VAT. Swapping the bases is a classic error.
Příklad. The rule is in the contract, not in the law: always read which base each deduction uses.
2 / 3
From work done to the amount payable
Value of work done at bill rates (VAT excluded) × (1 + 9 %) gives the tax-inclusive value. Deduct the advance recovery and the retention from it.
Unused provisional sum is not paid: it becomes payable only when the client orders work against it. A progress payment covers measured work and instructed work only.
Příklad. Retention is released after the defects liability period; the advance is fully recovered before completion.
Progress payment 1
Work measured in the first period, at bill rates without VAT.
Není v měřítku
Zadání
Work done ¥150,000.00. VAT 9 %.
Advance recovery: 10 % of the tax-inclusive value of the period. Retention: 3 % of the value without VAT.
Krok 1 z 4
Tax-inclusive value
Work × 1.09. What is it?
Nápověda: The rates hold every cost but VAT.
¥150,000.00 × 1.09 = ¥163,500.00.
Krok 2 z 4
Advance recovery
10 % of the tax-inclusive value. What is recovered?
Stručně. Each deduction on its own base: advance on the tax-inclusive value, retention on the value without VAT.
Zkontrolujte se
Otázka 1 z 3
Tax-inclusive value of a period 218,000.00 yuan; value without VAT 200,000.00. Advance recovery 10 % of the tax-inclusive value, retention 3 % of the value without VAT. What is payable?
218,000.00 − 21,800.00 − 6,000.00 = ¥190,200.00.
Otázka 2 z 3
A colleague takes retention on the tax-inclusive value. What happens?
The contract names the base, and it is the value without VAT.
Right.
A larger base withholds more.
Otázka 3 z 3
Is unused provisional sum included in a progress payment?
It is paid only when the client orders work against it.