OpenConstruction Academy
Sign in / Register
EN

Theory before task 4 · 10 min

Progress payment: advance recovery and retention on the right base

Interim payment and advance recovery

After this lecture you can

  1. Turn work done this period into its tax-inclusive value with VAT.
  2. Recover the advance pro rata on the tax-inclusive value, as the contract says.
  3. Withhold retention (质保金) on the value without VAT.
1 / 3

Two amounts kept back, two different bases

A progress payment (进度款) pays for work measured in the period. Two amounts come off it. The advance payment (预付款), paid at the start, is recovered in instalments; here the contract recovers it pro rata: 10 % of the tax-inclusive value of each period. Retention (质保金) is security for defects, held until the defects liability period ends; here it is 3 % of the value without VAT. Swapping the bases is a classic error.

Example. The rule is in the contract, not in the law: always read which base each deduction uses.
2 / 3

From work done to the amount payable

Value of work done at bill rates (VAT excluded) × (1 + 9 %) gives the tax-inclusive value. Deduct the advance recovery and the retention from it.

Example. 150,000.00 done, VAT 9 %: 150,000.00 × 1.09.
Work done, no VAT¥150,000.00
With VAT 9 %¥163,500.00
3 / 3

What is not paid

Unused provisional sum is not paid: it becomes payable only when the client orders work against it. A progress payment covers measured work and instructed work only.

Example. Retention is released after the defects liability period; the advance is fully recovered before completion.

Progress payment 1

Work measured in the first period, at bill rates without VAT.

Not to scale
The problem
  • Work done ¥150,000.00. VAT 9 %.
  • Advance recovery: 10 % of the tax-inclusive value of the period. Retention: 3 % of the value without VAT.
Step 1 of 4

Tax-inclusive value

Work × 1.09. What is it?

¥150,000.00 × 1.09 = ¥163,500.00.

Step 2 of 4

Advance recovery

10 % of the tax-inclusive value. What is recovered?

¥163,500.00 × 10 % = ¥16,350.00.

Step 3 of 4

Retention

3 % of the value without VAT. What is held?

¥150,000.00 × 3 % = ¥4,500.00.

¥163,5001−¥16,3502−¥4,5003?4
  • 1 Tax-inclusive value
  • 2 Advance
  • 3 Retention
  • 4 Payable
¥163,5001−¥16,3502−¥4,5003¥142,6504
  • 1 Tax-inclusive value
  • 2 Advance
  • 3 Retention
  • 4 Payable
Step 4 of 4

Amount payable

Tax-inclusive value less both. What is paid?

¥163,500.00 − ¥16,350.00 − ¥4,500.00 = ¥142,650.00.

In short. Each deduction on its own base: advance on the tax-inclusive value, retention on the value without VAT.

Check yourself

Question 1 of 3

Tax-inclusive value of a period 218,000.00 yuan; value without VAT 200,000.00. Advance recovery 10 % of the tax-inclusive value, retention 3 % of the value without VAT. What is payable?

218,000.00 − 21,800.00 − 6,000.00 = ¥190,200.00.
Question 2 of 3

A colleague takes retention on the tax-inclusive value. What happens?

  • The contract names the base, and it is the value without VAT.

  • Right.

  • A larger base withholds more.

Question 3 of 3

Is unused provisional sum included in a progress payment?

  • It is paid only when the client orders work against it.

  • Right.

  • Unused provisional sum is never paid.