OpenConstruction Academy
Σύνδεση / Εγγραφή
EL

Θεωρία πριν από την εργασία 1 · 9 λ.

The 28-day clock: awareness and the Notice of Claim

Πότε ξεκίνησε το ρολόι; Επίγνωση και οι 28 ημέρες

Εισαγωγή στο μάθημα

Μετά από αυτή τη διάλεξη μπορείτε να

  1. Say when the 28 days of FIDIC Sub-Clause 20.2.1 start: when the Contractor became aware, or should have become aware.
  2. Count calendar days across a month end without slipping a day.
  3. Record the event in the site diary on the day it happens.
1 / 3

Why a claim starts with a notice

Under the FIDIC Conditions of Contract for Construction (the Red Book, 2017 edition), a Contractor who considers itself entitled to more time or money must give the Engineer a Notice of Claim within 28 days after it became aware, or should have become aware, of the event (Sub-Clause 20.2.1). Miss it and the Contractor loses the entitlement, unless the late-notice route of 20.2.2 helps. The notice is short: it describes the event and says a claim is coming. The detail follows later.

Παράδειγμα. Days in FIDIC 2017 are calendar days (Sub-Clause 1.1.27). Weekends and public holidays count.
2 / 3

Aware, or should have been

The clock starts on the day the Contractor knew, or a competent contractor would have known, that the event was happening. Not when its cost was known, not when the delay ended, not when head office read the report. A crew standing idle on site because drawings are missing makes the Contractor aware that day. This is why the site diary matters: the entry of the day shows when awareness began and proves it later.

Παράδειγμα. Waiting for the cost to be clear before notifying is the commonest way to lose a claim.
3 / 3

Counting the days

Count from the day of awareness to the day the Engineer receives the notice. Work month by month: the days left in the first month, then the days in the second. Day 28 is the last day.

Παράδειγμα. Aware 18/10, notice received 06/11: 13 days to the end of October (31 days) plus 6 days in November = 19 days.
Days to 31 October13
Days in November6
Days elapsed19

Was the notice in time?

On 18/10/2027 a crew stands idle because the Engineer's revised drawings have not arrived. The Contractor's notice reaches the Engineer on 06/11/2027.

Όχι υπό κλίμακα
Το πρόβλημα
  • Awareness: 18 October 2027; the site diary of that day records the idle crew.
  • Notice received by the Engineer: 6 November 2027. October has 31 days.
Βήμα 1 από 2

Days elapsed

From 18 October to 6 November. How many days?

(31 − 18) + 6 = 19 days.

Βήμα 2 από 2

Days to spare

How many days remained before the 28-day limit?

28 − 19 = 9 days. The notice is in time.

Με λίγα λόγια. The clock starts on the day of awareness, recorded in the diary. Count calendar days. Notify early; detail later.

Ελέγξτε τον εαυτό σας

Ερώτηση 1 από 3

Aware on 25/01, notice received on 19/02 (January has 31 days). How many days elapsed?

(31 − 25) + 19 = 25 days: in time.
Ερώτηση 2 από 3

When does the 28-day period start?

  • Waiting for the cost loses the claim.

  • Right. Sub-Clause 20.2.1.

  • The event may last for weeks; the clock does not wait.

Ερώτηση 3 από 3

A Friday and a public holiday fall inside the 28 days. Do they count?

  • FIDIC 2017 counts calendar days.

  • Right. Sub-Clause 1.1.27.

  • Every calendar day counts.