OpenConstruction Academy
Кирүү / Катталуу
KY

1-тапшырма алдындагы теория · 9 мүн

The 28-day clock: awareness and the Notice of Claim

Саат качан башталды? Хабардар болуу жана 28 күн

Курска киришүү

Бул лекциядан кийин сиз төмөнкүнү үйрөнөсүз

  1. Say when the 28 days of FIDIC Sub-Clause 20.2.1 start: when the Contractor became aware, or should have become aware.
  2. Count calendar days across a month end without slipping a day.
  3. Record the event in the site diary on the day it happens.
1 / 3

Why a claim starts with a notice

Under the FIDIC Conditions of Contract for Construction (the Red Book, 2017 edition), a Contractor who considers itself entitled to more time or money must give the Engineer a Notice of Claim within 28 days after it became aware, or should have become aware, of the event (Sub-Clause 20.2.1). Miss it and the Contractor loses the entitlement, unless the late-notice route of 20.2.2 helps. The notice is short: it describes the event and says a claim is coming. The detail follows later.

Мисал. Days in FIDIC 2017 are calendar days (Sub-Clause 1.1.27). Weekends and public holidays count.
2 / 3

Aware, or should have been

The clock starts on the day the Contractor knew, or a competent contractor would have known, that the event was happening. Not when its cost was known, not when the delay ended, not when head office read the report. A crew standing idle on site because drawings are missing makes the Contractor aware that day. This is why the site diary matters: the entry of the day shows when awareness began and proves it later.

Мисал. Waiting for the cost to be clear before notifying is the commonest way to lose a claim.
3 / 3

Counting the days

Count from the day of awareness to the day the Engineer receives the notice. Work month by month: the days left in the first month, then the days in the second. Day 28 is the last day.

Мисал. Aware 18/10, notice received 06/11: 13 days to the end of October (31 days) plus 6 days in November = 19 days.
Days to 31 October13
Days in November6
Days elapsed19

Was the notice in time?

On 18/10/2027 a crew stands idle because the Engineer's revised drawings have not arrived. The Contractor's notice reaches the Engineer on 06/11/2027.

Масштабсыз
Маселе
  • Awareness: 18 October 2027; the site diary of that day records the idle crew.
  • Notice received by the Engineer: 6 November 2027. October has 31 days.
2 кадамдын 1-си

Days elapsed

From 18 October to 6 November. How many days?

(31 − 18) + 6 = 19 days.

2 кадамдын 2-си

Days to spare

How many days remained before the 28-day limit?

28 − 19 = 9 days. The notice is in time.

Кыскача. The clock starts on the day of awareness, recorded in the diary. Count calendar days. Notify early; detail later.

Өзүңүздү текшериңиз

3 суроонун 1-си

Aware on 25/01, notice received on 19/02 (January has 31 days). How many days elapsed?

(31 − 25) + 19 = 25 days: in time.
3 суроонун 2-си

When does the 28-day period start?

  • Waiting for the cost loses the claim.

  • Right. Sub-Clause 20.2.1.

  • The event may last for weeks; the clock does not wait.

3 суроонун 3-си

A Friday and a public holiday fall inside the 28 days. Do they count?

  • FIDIC 2017 counts calendar days.

  • Right. Sub-Clause 1.1.27.

  • Every calendar day counts.