Талаптар жана мөөнөттү узартуу (Сауд Арабиясы, FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

1-тапшырманы баштоо

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Ойдон чыгарылган долбоор
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
ERPдеги иш
Тапшырмалар: 5, болжол менен 1 саат 55 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idle1-тапшырма
    • Diary: rock in the drainage trench2-тапшырма
  • Project ManagerYour firm, programme and costs
    • The remaining programme3-тапшырма
    • Cost records4-тапшырма
СизClaims and contracts manager, the Contractor

Сизден кетет

    • Notices of Claim2-тапшырма
    • Extension of time and its basis3-тапшырма
    • Cost Plus Profit for NOC-024-тапшырма
    • The fully detailed Claim5-тапшырма
    The EngineerAdministers the contract for the Employer

Долбоор боюнча жолуңуз

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    1-тапшырма · 20 мүн

    Саат качан башталды? Хабардар болуу жана 28 күн

    Натыйжа
    The awareness date, and whether NOC-02 was in time
    Документ
    Daily diaries around the roof slab stoppage
    ERPде
    Daily Diary
  2. Notices

    2-тапшырма · 20 мүн

    Талап кылуу жөнүндө билдирүүлөр жана кечиккен Билдирүү

    Натыйжа
    Both Notices registered, and whether the late one stands
    Документ
    The Engineer's notice that NOC-01 was late
    ERPде
    Variations
  3. Time and money

    3-тапшырма · 30 мүн

    Кайсы кечигүү Аяктоону жылдырат? Критикалык жол

    Натыйжа
    The critical path and the delay that moves Completion
    Документ
    The remaining programme and both delays
    ERPде
    4D Schedule
  4. Time and money

    4-тапшырма · 30 мүн

    Кечиккен чиймелер үчүн Чыгым плюс пайда

    Натыйжа
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Документ
    Cost records: overheads, idle crew, formwork hire
    ERPде
    Variations
  5. Claim

    5-тапшырма · 15 мүн

    Толук деталдаштырылган Талап: 84 күн

    Натыйжа
    NOC-02 submitted as a fully detailed Claim
    Документ
    The claim file and the awareness date
    ERPде
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
1-тапшырмаAwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
2-тапшырмаLate NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
3-тапшырмаTimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
4-тапшырмаCost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.