Курска киришүү · 3 мүн
Талаптар жана мөөнөттү узартуу (Сауд Арабиясы, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Ойдон чыгарылган долбоор- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- ERPдеги иш
- Тапшырмалар: 5, болжол менен 1 саат 55 мүн
Ким кимге эмне берет
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idle1-тапшырма
- Diary: rock in the drainage trench2-тапшырма
- Project ManagerYour firm, programme and costs
- The remaining programme3-тапшырма
- Cost records4-тапшырма
Сизден кетет
- Notices of Claim2-тапшырма
- Extension of time and its basis3-тапшырма
- Cost Plus Profit for NOC-024-тапшырма
- The fully detailed Claim5-тапшырма
Долбоор боюнча жолуңуз
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
1-тапшырма · 20 мүн
Саат качан башталды? Хабардар болуу жана 28 күн
- Натыйжа
- The awareness date, and whether NOC-02 was in time
- Документ
- Daily diaries around the roof slab stoppage
- ERPде
- Daily Diary
Notices
2-тапшырма · 20 мүн
Талап кылуу жөнүндө билдирүүлөр жана кечиккен Билдирүү
- Натыйжа
- Both Notices registered, and whether the late one stands
- Документ
- The Engineer's notice that NOC-01 was late
- ERPде
- Variations
Time and money
3-тапшырма · 30 мүн
Кайсы кечигүү Аяктоону жылдырат? Критикалык жол
- Натыйжа
- The critical path and the delay that moves Completion
- Документ
- The remaining programme and both delays
- ERPде
- 4D Schedule
Time and money
4-тапшырма · 30 мүн
Кечиккен чиймелер үчүн Чыгым плюс пайда
- Натыйжа
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Документ
- Cost records: overheads, idle crew, formwork hire
- ERPде
- Variations
Claim
5-тапшырма · 15 мүн
Толук деталдаштырылган Талап: 84 күн
- Натыйжа
- NOC-02 submitted as a fully detailed Claim
- Документ
- The claim file and the awareness date
- ERPде
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.