Panimula ng kurso · 3 min
Mga claim at extension of time (Saudi Arabia, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Kathang-isip na proyekto- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- Trabaho sa ERP
- 5 gawain, mga 1 oras 55 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleGawain 1
- Diary: rock in the drainage trenchGawain 2
- Project ManagerYour firm, programme and costs
- The remaining programmeGawain 3
- Cost recordsGawain 4
Lumalabas sa iyo
- Notices of ClaimGawain 2
- Extension of time and its basisGawain 3
- Cost Plus Profit for NOC-02Gawain 4
- The fully detailed ClaimGawain 5
Ang ruta mo sa proyekto
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Gawain 1 · 20 min
Kailan nagsimula ang orasan? Ang pagkaalam at ang 28 araw
- Ang gagawin mo
- The awareness date, and whether NOC-02 was in time
- Dokumento
- Daily diaries around the roof slab stoppage
- Sa ERP
- Daily Diary
Notices
Gawain 2 · 20 min
Mga Notice of Claim at ang huling Notice
- Ang gagawin mo
- Both Notices registered, and whether the late one stands
- Dokumento
- The Engineer's notice that NOC-01 was late
- Sa ERP
- Variations
Time and money
Gawain 3 · 30 min
Aling pagkaantala ang nagpapalipat sa Completion? Ang kritikal na landas
- Ang gagawin mo
- The critical path and the delay that moves Completion
- Dokumento
- The remaining programme and both delays
- Sa ERP
- 4D Schedule
Time and money
Gawain 4 · 30 min
Cost Plus Profit para sa huling mga drawing
- Ang gagawin mo
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Dokumento
- Cost records: overheads, idle crew, formwork hire
- Sa ERP
- Variations
Claim
Gawain 5 · 15 min
Ang ganap na detalyadong Claim: 84 na araw
- Ang gagawin mo
- NOC-02 submitted as a fully detailed Claim
- Dokumento
- The claim file and the awareness date
- Sa ERP
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.