Mga claim at extension of time (Saudi Arabia, FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

Simulan ang gawain 1

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Kathang-isip na proyekto
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
Trabaho sa ERP
5 gawain, mga 1 oras 55 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idleGawain 1
    • Diary: rock in the drainage trenchGawain 2
  • Project ManagerYour firm, programme and costs
    • The remaining programmeGawain 3
    • Cost recordsGawain 4
IkawClaims and contracts manager, the Contractor

Lumalabas sa iyo

    • Notices of ClaimGawain 2
    • Extension of time and its basisGawain 3
    • Cost Plus Profit for NOC-02Gawain 4
    • The fully detailed ClaimGawain 5
    The EngineerAdministers the contract for the Employer

Ang ruta mo sa proyekto

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    Gawain 1 · 20 min

    Kailan nagsimula ang orasan? Ang pagkaalam at ang 28 araw

    Ang gagawin mo
    The awareness date, and whether NOC-02 was in time
    Dokumento
    Daily diaries around the roof slab stoppage
    Sa ERP
    Daily Diary
  2. Notices

    Gawain 2 · 20 min

    Mga Notice of Claim at ang huling Notice

    Ang gagawin mo
    Both Notices registered, and whether the late one stands
    Dokumento
    The Engineer's notice that NOC-01 was late
    Sa ERP
    Variations
  3. Time and money

    Gawain 3 · 30 min

    Aling pagkaantala ang nagpapalipat sa Completion? Ang kritikal na landas

    Ang gagawin mo
    The critical path and the delay that moves Completion
    Dokumento
    The remaining programme and both delays
    Sa ERP
    4D Schedule
  4. Time and money

    Gawain 4 · 30 min

    Cost Plus Profit para sa huling mga drawing

    Ang gagawin mo
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Dokumento
    Cost records: overheads, idle crew, formwork hire
    Sa ERP
    Variations
  5. Claim

    Gawain 5 · 15 min

    Ang ganap na detalyadong Claim: 84 na araw

    Ang gagawin mo
    NOC-02 submitted as a fully detailed Claim
    Dokumento
    The claim file and the awareness date
    Sa ERP
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
Gawain 1AwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
Gawain 2Late NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
Gawain 3TimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
Gawain 4Cost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.