ادعاها و تمدید مدت (عربستان سعودی، FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

شروع تکلیف 1

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.پروژهٔ خیالی
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
کار در ERP
5 تکلیف، حدود 1 ساعت 55 دقیقه

چه کسی چه چیزی به چه کسی می‌دهد

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

به شما می‌رسد

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idleتکلیف 1
    • Diary: rock in the drainage trenchتکلیف 2
  • Project ManagerYour firm, programme and costs
    • The remaining programmeتکلیف 3
    • Cost recordsتکلیف 4
شماClaims and contracts manager, the Contractor

از شما می‌رود

    • Notices of Claimتکلیف 2
    • Extension of time and its basisتکلیف 3
    • Cost Plus Profit for NOC-02تکلیف 4
    • The fully detailed Claimتکلیف 5
    The EngineerAdministers the contract for the Employer

مسیر شما در پروژه

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    تکلیف 1 · 20 دقیقه

    ساعت از کی شروع شد؟ آگاهی و 28 روز

    خروجی شما
    The awareness date, and whether NOC-02 was in time
    سند
    Daily diaries around the roof slab stoppage
    در ERP
    Daily Diary
  2. Notices

    تکلیف 2 · 20 دقیقه

    اخطارهای ادعا و اخطار دیررس

    خروجی شما
    Both Notices registered, and whether the late one stands
    سند
    The Engineer's notice that NOC-01 was late
    در ERP
    Variations
  3. Time and money

    تکلیف 3 · 30 دقیقه

    کدام تأخیر تکمیل را جابه‌جا می‌کند؟ مسیر بحرانی

    خروجی شما
    The critical path and the delay that moves Completion
    سند
    The remaining programme and both delays
    در ERP
    4D Schedule
  4. Time and money

    تکلیف 4 · 30 دقیقه

    هزینه به‌علاوه سود برای نقشه‌های دیررس

    خروجی شما
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    سند
    Cost records: overheads, idle crew, formwork hire
    در ERP
    Variations
  5. Claim

    تکلیف 5 · 15 دقیقه

    ادعای کاملاً مستند: 84 روز

    خروجی شما
    NOC-02 submitted as a fully detailed Claim
    سند
    The claim file and the awareness date
    در ERP
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
تکلیف 1AwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
تکلیف 2Late NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
تکلیف 3TimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
تکلیف 4Cost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

آبی چیزی است که تکلیف اضافه می‌کند؛ خاکستری از مرحلهٔ قبل آمده است.

به‌طور خلاصه. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.