معرفی دوره · 3 دقیقه
ادعاها و تمدید مدت (عربستان سعودی، FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
پروژهٔ خیالی- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- کار در ERP
- 5 تکلیف، حدود 1 ساعت 55 دقیقه
چه کسی چه چیزی به چه کسی میدهد
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
به شما میرسد
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleتکلیف 1
- Diary: rock in the drainage trenchتکلیف 2
- Project ManagerYour firm, programme and costs
- The remaining programmeتکلیف 3
- Cost recordsتکلیف 4
از شما میرود
- Notices of Claimتکلیف 2
- Extension of time and its basisتکلیف 3
- Cost Plus Profit for NOC-02تکلیف 4
- The fully detailed Claimتکلیف 5
مسیر شما در پروژه
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
تکلیف 1 · 20 دقیقه
ساعت از کی شروع شد؟ آگاهی و 28 روز
- خروجی شما
- The awareness date, and whether NOC-02 was in time
- سند
- Daily diaries around the roof slab stoppage
- در ERP
- Daily Diary
Notices
تکلیف 2 · 20 دقیقه
اخطارهای ادعا و اخطار دیررس
- خروجی شما
- Both Notices registered, and whether the late one stands
- سند
- The Engineer's notice that NOC-01 was late
- در ERP
- Variations
Time and money
تکلیف 3 · 30 دقیقه
کدام تأخیر تکمیل را جابهجا میکند؟ مسیر بحرانی
- خروجی شما
- The critical path and the delay that moves Completion
- سند
- The remaining programme and both delays
- در ERP
- 4D Schedule
Time and money
تکلیف 4 · 30 دقیقه
هزینه بهعلاوه سود برای نقشههای دیررس
- خروجی شما
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- سند
- Cost records: overheads, idle crew, formwork hire
- در ERP
- Variations
Claim
تکلیف 5 · 15 دقیقه
ادعای کاملاً مستند: 84 روز
- خروجی شما
- NOC-02 submitted as a fully detailed Claim
- سند
- The claim file and the awareness date
- در ERP
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
آبی چیزی است که تکلیف اضافه میکند؛ خاکستری از مرحلهٔ قبل آمده است.
بهطور خلاصه. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.