Uvod u tečaj · 3 min
Potraživanja i produljenje roka (Saudijska Arabija, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Izmišljeni projekt- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- Rad u ERP-u
- Zadataka: 5, oko 1 h 55 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleZadatak 1
- Diary: rock in the drainage trenchZadatak 2
- Project ManagerYour firm, programme and costs
- The remaining programmeZadatak 3
- Cost recordsZadatak 4
Odlazi od vas
- Notices of ClaimZadatak 2
- Extension of time and its basisZadatak 3
- Cost Plus Profit for NOC-02Zadatak 4
- The fully detailed ClaimZadatak 5
Vaš put kroz projekt
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Zadatak 1 · 20 min
Kada je sat počeo teći? Saznanje i 28 dana
- Vaš rezultat
- The awareness date, and whether NOC-02 was in time
- Dokument
- Daily diaries around the roof slab stoppage
- U ERP-u
- Daily Diary
Notices
Zadatak 2 · 20 min
Obavijesti o potraživanju i zakašnjela Obavijest
- Vaš rezultat
- Both Notices registered, and whether the late one stands
- Dokument
- The Engineer's notice that NOC-01 was late
- U ERP-u
- Variations
Time and money
Zadatak 3 · 30 min
Koje kašnjenje pomiče Dovršetak? Kritični put
- Vaš rezultat
- The critical path and the delay that moves Completion
- Dokument
- The remaining programme and both delays
- U ERP-u
- 4D Schedule
Time and money
Zadatak 4 · 30 min
Trošak plus dobit za zakašnjele nacrte
- Vaš rezultat
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Dokument
- Cost records: overheads, idle crew, formwork hire
- U ERP-u
- Variations
Claim
Zadatak 5 · 15 min
Potpuno obrazloženo Potraživanje: 84 dana
- Vaš rezultat
- NOC-02 submitted as a fully detailed Claim
- Dokument
- The claim file and the awareness date
- U ERP-u
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.