Introduktion til kurset · 3 min
Krav og tidsfristforlængelse (Saudi-Arabien, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Fiktivt projekt- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- Arbejde i ERP
- 5 opgaver, cirka 1 t 55 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleOpgave 1
- Diary: rock in the drainage trenchOpgave 2
- Project ManagerYour firm, programme and costs
- The remaining programmeOpgave 3
- Cost recordsOpgave 4
Går fra dig
- Notices of ClaimOpgave 2
- Extension of time and its basisOpgave 3
- Cost Plus Profit for NOC-02Opgave 4
- The fully detailed ClaimOpgave 5
Din vej gennem sagen
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Opgave 1 · 20 min
Hvornår startede uret? Erkendelse og de 28 dage
- Du leverer
- The awareness date, and whether NOC-02 was in time
- Dokument
- Daily diaries around the roof slab stoppage
- I ERP
- Daily Diary
Notices
Opgave 2 · 20 min
Varsler om krav og det forsinkede varsel
- Du leverer
- Both Notices registered, and whether the late one stands
- Dokument
- The Engineer's notice that NOC-01 was late
- I ERP
- Variations
Time and money
Opgave 3 · 30 min
Hvilken forsinkelse flytter Færdiggørelse? Den kritiske vej
- Du leverer
- The critical path and the delay that moves Completion
- Dokument
- The remaining programme and both delays
- I ERP
- 4D Schedule
Time and money
Opgave 4 · 30 min
Omkostning plus fortjeneste for de forsinkede tegninger
- Du leverer
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Dokument
- Cost records: overheads, idle crew, formwork hire
- I ERP
- Variations
Claim
Opgave 5 · 15 min
Det fuldt detaljerede krav: 84 dage
- Du leverer
- NOC-02 submitted as a fully detailed Claim
- Dokument
- The claim file and the awareness date
- I ERP
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.