Сургалтын танилцуулга · 3 мин

Нэхэмжлэл ба хугацаа сунгалт (Саудын Араб, FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

1-р даалгаврыг эхлэх

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Зохиомол төсөл
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 1 цаг 55 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idleДаалгавар 1
    • Diary: rock in the drainage trenchДаалгавар 2
  • Project ManagerYour firm, programme and costs
    • The remaining programmeДаалгавар 3
    • Cost recordsДаалгавар 4
ТаClaims and contracts manager, the Contractor

Танаас гардаг

    • Notices of ClaimДаалгавар 2
    • Extension of time and its basisДаалгавар 3
    • Cost Plus Profit for NOC-02Даалгавар 4
    • The fully detailed ClaimДаалгавар 5
    The EngineerAdministers the contract for the Employer

Төслөөр явах таны зам

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    Даалгавар 1 · 20 мин

    Цаг хэзээ эхэлсэн бэ? Мэдсэн огноо ба 28 хоног

    Үр дүн
    The awareness date, and whether NOC-02 was in time
    Баримт бичиг
    Daily diaries around the roof slab stoppage
    ERP дээр
    Daily Diary
  2. Notices

    Даалгавар 2 · 20 мин

    Нэхэмжлэлийн мэдэгдлүүд ба хоцорсон мэдэгдэл

    Үр дүн
    Both Notices registered, and whether the late one stands
    Баримт бичиг
    The Engineer's notice that NOC-01 was late
    ERP дээр
    Variations
  3. Time and money

    Даалгавар 3 · 30 мин

    Аль саатал Дуусгалтыг түлхэх вэ? Эгзэгтэй зам

    Үр дүн
    The critical path and the delay that moves Completion
    Баримт бичиг
    The remaining programme and both delays
    ERP дээр
    4D Schedule
  4. Time and money

    Даалгавар 4 · 30 мин

    Хоцорсон зургийн Зардал ба ашиг

    Үр дүн
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Баримт бичиг
    Cost records: overheads, idle crew, formwork hire
    ERP дээр
    Variations
  5. Claim

    Даалгавар 5 · 15 мин

    Бүрэн нарийвчилсан Нэхэмжлэл: 84 хоног

    Үр дүн
    NOC-02 submitted as a fully detailed Claim
    Баримт бичиг
    The claim file and the awareness date
    ERP дээр
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
Даалгавар 1AwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
Даалгавар 2Late NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
Даалгавар 3TimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
Даалгавар 4Cost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.