Сургалтын танилцуулга · 3 мин
Нэхэмжлэл ба хугацаа сунгалт (Саудын Араб, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Зохиомол төсөл- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- ERP дээрх ажил
- Даалгавар: 5, ойролцоогоор 1 цаг 55 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleДаалгавар 1
- Diary: rock in the drainage trenchДаалгавар 2
- Project ManagerYour firm, programme and costs
- The remaining programmeДаалгавар 3
- Cost recordsДаалгавар 4
Танаас гардаг
- Notices of ClaimДаалгавар 2
- Extension of time and its basisДаалгавар 3
- Cost Plus Profit for NOC-02Даалгавар 4
- The fully detailed ClaimДаалгавар 5
Төслөөр явах таны зам
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Даалгавар 1 · 20 мин
Цаг хэзээ эхэлсэн бэ? Мэдсэн огноо ба 28 хоног
- Үр дүн
- The awareness date, and whether NOC-02 was in time
- Баримт бичиг
- Daily diaries around the roof slab stoppage
- ERP дээр
- Daily Diary
Notices
Даалгавар 2 · 20 мин
Нэхэмжлэлийн мэдэгдлүүд ба хоцорсон мэдэгдэл
- Үр дүн
- Both Notices registered, and whether the late one stands
- Баримт бичиг
- The Engineer's notice that NOC-01 was late
- ERP дээр
- Variations
Time and money
Даалгавар 3 · 30 мин
Аль саатал Дуусгалтыг түлхэх вэ? Эгзэгтэй зам
- Үр дүн
- The critical path and the delay that moves Completion
- Баримт бичиг
- The remaining programme and both delays
- ERP дээр
- 4D Schedule
Time and money
Даалгавар 4 · 30 мин
Хоцорсон зургийн Зардал ба ашиг
- Үр дүн
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Баримт бичиг
- Cost records: overheads, idle crew, formwork hire
- ERP дээр
- Variations
Claim
Даалгавар 5 · 15 мин
Бүрэн нарийвчилсан Нэхэмжлэл: 84 хоног
- Үр дүн
- NOC-02 submitted as a fully detailed Claim
- Баримт бичиг
- The claim file and the awareness date
- ERP дээр
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.