Nõuded ja tähtaja pikendamine (Saudi Araabia, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Väljamõeldud projekt- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- Töö ERP-s
- Ülesandeid 5, umbes 1 h 55 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleÜlesanne 1
- Diary: rock in the drainage trenchÜlesanne 2
- Project ManagerYour firm, programme and costs
- The remaining programmeÜlesanne 3
- Cost recordsÜlesanne 4
Läheb sinult
- Notices of ClaimÜlesanne 2
- Extension of time and its basisÜlesanne 3
- Cost Plus Profit for NOC-02Ülesanne 4
- The fully detailed ClaimÜlesanne 5
Sinu tee läbi projekti
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Ülesanne 1 · 20 min
Millal kell käima läks? Teadlikkus ja 28 päeva
- Sinu tulemus
- The awareness date, and whether NOC-02 was in time
- Dokument
- Daily diaries around the roof slab stoppage
- ERP-s
- Daily Diary
Notices
Ülesanne 2 · 20 min
Nõudeteated ja hilinenud teade
- Sinu tulemus
- Both Notices registered, and whether the late one stands
- Dokument
- The Engineer's notice that NOC-01 was late
- ERP-s
- Variations
Time and money
Ülesanne 3 · 30 min
Milline viivitus lükkab Valmimist edasi? Kriitiline tee
- Sinu tulemus
- The critical path and the delay that moves Completion
- Dokument
- The remaining programme and both delays
- ERP-s
- 4D Schedule
Time and money
Ülesanne 4 · 30 min
Kulu pluss kasum hilinenud jooniste eest
- Sinu tulemus
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Dokument
- Cost records: overheads, idle crew, formwork hire
- ERP-s
- Variations
Claim
Ülesanne 5 · 15 min
Täielikult põhjendatud Nõue: 84 päeva
- Sinu tulemus
- NOC-02 submitted as a fully detailed Claim
- Dokument
- The claim file and the awareness date
- ERP-s
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.