Course introduction · 3 min
Claims and extension of time (Saudi Arabia, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Fictional project- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- Work in the ERP
- 5 tasks, about 1 h 55 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleTask 1
- Diary: rock in the drainage trenchTask 2
- Project ManagerYour firm, programme and costs
- The remaining programmeTask 3
- Cost recordsTask 4
Goes from you
- Notices of ClaimTask 2
- Extension of time and its basisTask 3
- Cost Plus Profit for NOC-02Task 4
- The fully detailed ClaimTask 5
Your route through the job
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Task 1 · 20 min
When did the clock start? Awareness and the 28 days
- You produce
- The awareness date, and whether NOC-02 was in time
- Document
- Daily diaries around the roof slab stoppage
- In the ERP
- Daily Diary
Notices
Task 2 · 20 min
Notices of Claim and the late Notice
- You produce
- Both Notices registered, and whether the late one stands
- Document
- The Engineer's notice that NOC-01 was late
- In the ERP
- Variations
Time and money
Task 3 · 30 min
Which delay moves Completion? The critical path
- You produce
- The critical path and the delay that moves Completion
- Document
- The remaining programme and both delays
- In the ERP
- 4D Schedule
Time and money
Task 4 · 30 min
Cost Plus Profit for the late drawings
- You produce
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Document
- Cost records: overheads, idle crew, formwork hire
- In the ERP
- Variations
Claim
Task 5 · 15 min
The fully detailed Claim: 84 days
- You produce
- NOC-02 submitted as a fully detailed Claim
- Document
- The claim file and the awareness date
- In the ERP
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Blue is what the task adds; grey is carried over from before.
In short. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.