Course introduction · 3 min

Claims and extension of time (Saudi Arabia, FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

Start task 1

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Fictional project
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
Work in the ERP
5 tasks, about 1 h 55 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idleTask 1
    • Diary: rock in the drainage trenchTask 2
  • Project ManagerYour firm, programme and costs
    • The remaining programmeTask 3
    • Cost recordsTask 4
YouClaims and contracts manager, the Contractor

Goes from you

    • Notices of ClaimTask 2
    • Extension of time and its basisTask 3
    • Cost Plus Profit for NOC-02Task 4
    • The fully detailed ClaimTask 5
    The EngineerAdministers the contract for the Employer

Your route through the job

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    Task 1 · 20 min

    When did the clock start? Awareness and the 28 days

    You produce
    The awareness date, and whether NOC-02 was in time
    Document
    Daily diaries around the roof slab stoppage
    In the ERP
    Daily Diary
  2. Notices

    Task 2 · 20 min

    Notices of Claim and the late Notice

    You produce
    Both Notices registered, and whether the late one stands
    Document
    The Engineer's notice that NOC-01 was late
    In the ERP
    Variations
  3. Time and money

    Task 3 · 30 min

    Which delay moves Completion? The critical path

    You produce
    The critical path and the delay that moves Completion
    Document
    The remaining programme and both delays
    In the ERP
    4D Schedule
  4. Time and money

    Task 4 · 30 min

    Cost Plus Profit for the late drawings

    You produce
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Document
    Cost records: overheads, idle crew, formwork hire
    In the ERP
    Variations
  5. Claim

    Task 5 · 15 min

    The fully detailed Claim: 84 days

    You produce
    NOC-02 submitted as a fully detailed Claim
    Document
    The claim file and the awareness date
    In the ERP
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
Task 1AwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
Task 2Late NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
Task 3TimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
Task 4Cost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Blue is what the task adds; grey is carried over from before.

In short. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.