Introduktion till kursen · 3 min

Krav och tidsförlängning (Saudiarabien, FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

Starta uppgift 1

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Fiktivt projekt
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
Arbete i ERP
5 uppgifter, cirka 1 h 55 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idleUppgift 1
    • Diary: rock in the drainage trenchUppgift 2
  • Project ManagerYour firm, programme and costs
    • The remaining programmeUppgift 3
    • Cost recordsUppgift 4
DuClaims and contracts manager, the Contractor

Går från dig

    • Notices of ClaimUppgift 2
    • Extension of time and its basisUppgift 3
    • Cost Plus Profit for NOC-02Uppgift 4
    • The fully detailed ClaimUppgift 5
    The EngineerAdministers the contract for the Employer

Din väg genom projektet

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    Uppgift 1 · 20 min

    När startade klockan? Kännedom och de 28 dagarna

    Du tar fram
    The awareness date, and whether NOC-02 was in time
    Dokument
    Daily diaries around the roof slab stoppage
    I ERP
    Daily Diary
  2. Notices

    Uppgift 2 · 20 min

    Underrättelser om krav och den försenade underrättelsen

    Du tar fram
    Both Notices registered, and whether the late one stands
    Dokument
    The Engineer's notice that NOC-01 was late
    I ERP
    Variations
  3. Time and money

    Uppgift 3 · 30 min

    Vilken försening flyttar färdigställandet? Den kritiska vägen

    Du tar fram
    The critical path and the delay that moves Completion
    Dokument
    The remaining programme and both delays
    I ERP
    4D Schedule
  4. Time and money

    Uppgift 4 · 30 min

    Kostnad plus vinst för de försenade ritningarna

    Du tar fram
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Dokument
    Cost records: overheads, idle crew, formwork hire
    I ERP
    Variations
  5. Claim

    Uppgift 5 · 15 min

    Det fullständiga kravet: 84 dagar

    Du tar fram
    NOC-02 submitted as a fully detailed Claim
    Dokument
    The claim file and the awareness date
    I ERP
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
Uppgift 1AwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
Uppgift 2Late NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
Uppgift 3TimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
Uppgift 4Cost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.