Claims en bouwtijdverlenging (Saoedi-Arabië, FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

Start opdracht 1

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Fictief project
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
Werk in de ERP
5 opdrachten, ongeveer 1 u 55 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idleOpdracht 1
    • Diary: rock in the drainage trenchOpdracht 2
  • Project ManagerYour firm, programme and costs
    • The remaining programmeOpdracht 3
    • Cost recordsOpdracht 4
UClaims and contracts manager, the Contractor

Gaat van u uit

    • Notices of ClaimOpdracht 2
    • Extension of time and its basisOpdracht 3
    • Cost Plus Profit for NOC-02Opdracht 4
    • The fully detailed ClaimOpdracht 5
    The EngineerAdministers the contract for the Employer

Uw route door het project

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    Opdracht 1 · 20 min

    Wanneer begon de klok te tikken? Bewustwording en de 28 dagen

    U levert
    The awareness date, and whether NOC-02 was in time
    Document
    Daily diaries around the roof slab stoppage
    In de ERP
    Daily Diary
  2. Notices

    Opdracht 2 · 20 min

    Kennisgevingen van claim en de te late kennisgeving

    U levert
    Both Notices registered, and whether the late one stands
    Document
    The Engineer's notice that NOC-01 was late
    In de ERP
    Variations
  3. Time and money

    Opdracht 3 · 30 min

    Welke vertraging verschuift de Oplevering? Het kritieke pad

    U levert
    The critical path and the delay that moves Completion
    Document
    The remaining programme and both delays
    In de ERP
    4D Schedule
  4. Time and money

    Opdracht 4 · 30 min

    Kosten plus Winst voor de late tekeningen

    U levert
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Document
    Cost records: overheads, idle crew, formwork hire
    In de ERP
    Variations
  5. Claim

    Opdracht 5 · 15 min

    De volledig gedetailleerde Claim: 84 dagen

    U levert
    NOC-02 submitted as a fully detailed Claim
    Document
    The claim file and the awareness date
    In de ERP
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
Opdracht 1AwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
Opdracht 2Late NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
Opdracht 3TimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
Opdracht 4Cost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.