Inleiding tot de cursus · 3 min
Claims en bouwtijdverlenging (Saoedi-Arabië, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Fictief project- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- Werk in de ERP
- 5 opdrachten, ongeveer 1 u 55 min
Wie geeft wat aan wie
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Komt bij u
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleOpdracht 1
- Diary: rock in the drainage trenchOpdracht 2
- Project ManagerYour firm, programme and costs
- The remaining programmeOpdracht 3
- Cost recordsOpdracht 4
Gaat van u uit
- Notices of ClaimOpdracht 2
- Extension of time and its basisOpdracht 3
- Cost Plus Profit for NOC-02Opdracht 4
- The fully detailed ClaimOpdracht 5
Uw route door het project
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Opdracht 1 · 20 min
Wanneer begon de klok te tikken? Bewustwording en de 28 dagen
- U levert
- The awareness date, and whether NOC-02 was in time
- Document
- Daily diaries around the roof slab stoppage
- In de ERP
- Daily Diary
Notices
Opdracht 2 · 20 min
Kennisgevingen van claim en de te late kennisgeving
- U levert
- Both Notices registered, and whether the late one stands
- Document
- The Engineer's notice that NOC-01 was late
- In de ERP
- Variations
Time and money
Opdracht 3 · 30 min
Welke vertraging verschuift de Oplevering? Het kritieke pad
- U levert
- The critical path and the delay that moves Completion
- Document
- The remaining programme and both delays
- In de ERP
- 4D Schedule
Time and money
Opdracht 4 · 30 min
Kosten plus Winst voor de late tekeningen
- U levert
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Document
- Cost records: overheads, idle crew, formwork hire
- In de ERP
- Variations
Claim
Opdracht 5 · 15 min
De volledig gedetailleerde Claim: 84 dagen
- U levert
- NOC-02 submitted as a fully detailed Claim
- Document
- The claim file and the awareness date
- In de ERP
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.
Kort gezegd. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.