Nároky a prodloužení lhůty (Saúdská Arábie, FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

Začít úlohu 1

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Smyšlený projekt
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
Práce v ERP
Úlohy: 5, asi 1 h 55 min

Kdo komu co předává

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Přichází k vám

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idleÚloha 1
    • Diary: rock in the drainage trenchÚloha 2
  • Project ManagerYour firm, programme and costs
    • The remaining programmeÚloha 3
    • Cost recordsÚloha 4
VyClaims and contracts manager, the Contractor

Odchází od vás

    • Notices of ClaimÚloha 2
    • Extension of time and its basisÚloha 3
    • Cost Plus Profit for NOC-02Úloha 4
    • The fully detailed ClaimÚloha 5
    The EngineerAdministers the contract for the Employer

Vaše cesta zakázkou

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    Úloha 1 · 20 min

    Kdy začal běžet čas? Zjištění a 28 dnů

    Výstup
    The awareness date, and whether NOC-02 was in time
    Dokument
    Daily diaries around the roof slab stoppage
    V ERP
    Daily Diary
  2. Notices

    Úloha 2 · 20 min

    Oznámení o nároku a opožděné Oznámení

    Výstup
    Both Notices registered, and whether the late one stands
    Dokument
    The Engineer's notice that NOC-01 was late
    V ERP
    Variations
  3. Time and money

    Úloha 3 · 30 min

    Které zdržení posune Dokončení? Kritická cesta

    Výstup
    The critical path and the delay that moves Completion
    Dokument
    The remaining programme and both delays
    V ERP
    4D Schedule
  4. Time and money

    Úloha 4 · 30 min

    Náklady plus zisk za pozdní výkresy

    Výstup
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Dokument
    Cost records: overheads, idle crew, formwork hire
    V ERP
    Variations
  5. Claim

    Úloha 5 · 15 min

    Plně podložený claim: 84 dnů

    Výstup
    NOC-02 submitted as a fully detailed Claim
    Dokument
    The claim file and the awareness date
    V ERP
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
Úloha 1AwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
Úloha 2Late NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
Úloha 3TimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
Úloha 4Cost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.

Stručně. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.