Introducere în curs · 3 min

Revendicări și prelungirea termenului (Arabia Saudită, FIDIC)

You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

Începe sarcina 1

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Proiect fictiv
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
Lucru în ERP
5 sarcini, circa 1 h 55 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idleSarcina 1
    • Diary: rock in the drainage trenchSarcina 2
  • Project ManagerYour firm, programme and costs
    • The remaining programmeSarcina 3
    • Cost recordsSarcina 4
TuClaims and contracts manager, the Contractor

Pleacă de la tine

    • Notices of ClaimSarcina 2
    • Extension of time and its basisSarcina 3
    • Cost Plus Profit for NOC-02Sarcina 4
    • The fully detailed ClaimSarcina 5
    The EngineerAdministers the contract for the Employer

Traseul tău prin proiect

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    Sarcina 1 · 20 min

    Când a pornit ceasul? Luarea la cunoștință și cele 28 de zile

    Produci
    The awareness date, and whether NOC-02 was in time
    Document
    Daily diaries around the roof slab stoppage
    În ERP
    Daily Diary
  2. Notices

    Sarcina 2 · 20 min

    Notificările de Revendicare și Notificarea tardivă

    Produci
    Both Notices registered, and whether the late one stands
    Document
    The Engineer's notice that NOC-01 was late
    În ERP
    Variations
  3. Time and money

    Sarcina 3 · 30 min

    Care întârziere mută Finalizarea? Calea critică

    Produci
    The critical path and the delay that moves Completion
    Document
    The remaining programme and both delays
    În ERP
    4D Schedule
  4. Time and money

    Sarcina 4 · 30 min

    Cost plus Profit pentru planșele întârziate

    Produci
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Document
    Cost records: overheads, idle crew, formwork hire
    În ERP
    Variations
  5. Claim

    Sarcina 5 · 15 min

    Revendicarea complet detaliată: 84 de zile

    Produci
    NOC-02 submitted as a fully detailed Claim
    Document
    The claim file and the awareness date
    În ERP
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
Sarcina 1AwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
Sarcina 2Late NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
Sarcina 3TimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
Sarcina 4Cost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.