Revendicări și prelungirea termenului (Arabia Saudită, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Proiect fictiv- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- Lucru în ERP
- 5 sarcini, circa 1 h 55 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleSarcina 1
- Diary: rock in the drainage trenchSarcina 2
- Project ManagerYour firm, programme and costs
- The remaining programmeSarcina 3
- Cost recordsSarcina 4
Pleacă de la tine
- Notices of ClaimSarcina 2
- Extension of time and its basisSarcina 3
- Cost Plus Profit for NOC-02Sarcina 4
- The fully detailed ClaimSarcina 5
Traseul tău prin proiect
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Sarcina 1 · 20 min
Când a pornit ceasul? Luarea la cunoștință și cele 28 de zile
- Produci
- The awareness date, and whether NOC-02 was in time
- Document
- Daily diaries around the roof slab stoppage
- În ERP
- Daily Diary
Notices
Sarcina 2 · 20 min
Notificările de Revendicare și Notificarea tardivă
- Produci
- Both Notices registered, and whether the late one stands
- Document
- The Engineer's notice that NOC-01 was late
- În ERP
- Variations
Time and money
Sarcina 3 · 30 min
Care întârziere mută Finalizarea? Calea critică
- Produci
- The critical path and the delay that moves Completion
- Document
- The remaining programme and both delays
- În ERP
- 4D Schedule
Time and money
Sarcina 4 · 30 min
Cost plus Profit pentru planșele întârziate
- Produci
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Document
- Cost records: overheads, idle crew, formwork hire
- În ERP
- Variations
Claim
Sarcina 5 · 15 min
Revendicarea complet detaliată: 84 de zile
- Produci
- NOC-02 submitted as a fully detailed Claim
- Document
- The claim file and the awareness date
- În ERP
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.