Въведение в курса · 3 мин
Искове и удължаване на срока (Саудитска Арабия, FIDIC)
You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.
Измислен проект- Building
- Outpatient clinic for a private healthcare company
- Contract
- FIDIC Red Book 2017, the international standard contract, with Particular Conditions
- Money
- Saudi riyal, valued before VAT
- Работа в ERP
- Задачи: 5, около 1 ч 55 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- Site EngineerYour firm, keeps the diary
- Diary: roof slab crew idleЗадача 1
- Diary: rock in the drainage trenchЗадача 2
- Project ManagerYour firm, programme and costs
- The remaining programmeЗадача 3
- Cost recordsЗадача 4
Тръгва от вас
- Notices of ClaimЗадача 2
- Extension of time and its basisЗадача 3
- Cost Plus Profit for NOC-02Задача 4
- The fully detailed ClaimЗадача 5
Вашият път през проекта
Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.
Notices
Задача 1 · 20 мин
Кога започна да тече срокът? Узнаване и 28-те дни
- Вашият резултат
- The awareness date, and whether NOC-02 was in time
- Документ
- Daily diaries around the roof slab stoppage
- В ERP
- Daily Diary
Notices
Задача 2 · 20 мин
Уведомления за претенция и закъснялото Уведомление
- Вашият резултат
- Both Notices registered, and whether the late one stands
- Документ
- The Engineer's notice that NOC-01 was late
- В ERP
- Variations
Time and money
Задача 3 · 30 мин
Кое забавяне измества Завършването? Критичният път
- Вашият резултат
- The critical path and the delay that moves Completion
- Документ
- The remaining programme and both delays
- В ERP
- 4D Schedule
Time and money
Задача 4 · 30 мин
Стойност плюс печалба за закъснелите чертежи
- Вашият резултат
- Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
- Документ
- Cost records: overheads, idle crew, formwork hire
- В ERP
- Variations
Claim
Задача 5 · 15 мин
Напълно подробният Иск: 84 дни
- Вашият резултат
- NOC-02 submitted as a fully detailed Claim
- Документ
- The claim file and the awareness date
- В ERP
- Variations
Four tests a claim must pass
Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.