You manage claims for the builder of a three-storey clinic in Saudi Arabia. A claim is a formal request for more time or more money when something outside your control delays the job, such as drawings arriving late. In five tasks, under the FIDIC Red Book 2017 contract, you take two delays from the site diary to a fully detailed Claim: find when the notice clock started, test the Notices, find which delay moves Completion and price it.

1-тапсырманы бастау

A three-storey concrete frame with block infill walls and props still standing on the top floor, two workers in blue coveralls and white helmets walking across sandy ground.Ойдан шығарылған жоба
Al Nakhlah ClinicThree-storey outpatient clinic · roof slab stage
Building
Outpatient clinic for a private healthcare company
Contract
FIDIC Red Book 2017, the international standard contract, with Particular Conditions
Money
Saudi riyal, valued before VAT
ERP-дегі жұмыс
Тапсырмалар: 5, шамамен 1 сағ 55 мин

Кім кімге не береді

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сізге келеді

  • Site EngineerYour firm, keeps the diary
    • Diary: roof slab crew idle1-тапсырма
    • Diary: rock in the drainage trench2-тапсырма
  • Project ManagerYour firm, programme and costs
    • The remaining programme3-тапсырма
    • Cost records4-тапсырма
СізClaims and contracts manager, the Contractor

Сізден кетеді

    • Notices of Claim2-тапсырма
    • Extension of time and its basis3-тапсырма
    • Cost Plus Profit for NOC-024-тапсырма
    • The fully detailed Claim5-тапсырма
    The EngineerAdministers the contract for the Employer

Жоба бойынша жолыңыз

Two tasks get the Notices right, two find the time and the money, one sends the fully detailed Claim before its limit. Start with task 1: you read the site diaries to fix the date the builder became aware of the delay.

  1. Notices

    1-тапсырма · 20 мин

    Сағат қашан басталды? Хабардар болу және 28 күн

    Нәтиже
    The awareness date, and whether NOC-02 was in time
    Құжат
    Daily diaries around the roof slab stoppage
    ERP-де
    Daily Diary
  2. Notices

    2-тапсырма · 20 мин

    Талап туралы хабарламалар және кешіккен хабарлама

    Нәтиже
    Both Notices registered, and whether the late one stands
    Құжат
    The Engineer's notice that NOC-01 was late
    ERP-де
    Variations
  3. Time and money

    3-тапсырма · 30 мин

    Қай кідіріс Аяқталуды жылжытады? Сыни жол

    Нәтиже
    The critical path and the delay that moves Completion
    Құжат
    The remaining programme and both delays
    ERP-де
    4D Schedule
  4. Time and money

    4-тапсырма · 30 мин

    Кеш сызбалар үшін Шығын плюс пайда

    Нәтиже
    Cost Plus Profit (cost, plus a profit margin) for the late drawings, before VAT
    Құжат
    Cost records: overheads, idle crew, formwork hire
    ERP-де
    Variations
  5. Claim

    5-тапсырма · 15 мин

    Толық егжей-тегжейлі Талап: 84 күн

    Нәтиже
    NOC-02 submitted as a fully detailed Claim
    Құжат
    The claim file and the awareness date
    ERP-де
    Variations

Four tests a claim must pass

Each bar is one test, in the order of the tasks. Task 5 then puts what passed into the fully detailed Claim before the last time limit.

Notified too lateNotified in time
1-тапсырмаAwarenessThe Notice period runs from when the Contractor became aware, or should have. The diary fixes that date, not the letter.
Late, rejected in timeLate, not rejected in timeIn time
2-тапсырмаLate NoticeA late Notice still stands unless the Engineer, who runs the contract for the client, says it is late within its own period. Count both clocks.
Taken up by floatExtension of time
3-тапсырмаTimeOnly delay on the critical path, the chain of work that sets the finish, moves Completion. Delay that float (spare time) absorbs earns no extra time.
ProfitOverheads, idle crew, hire
4-тапсырмаCost Plus ProfitLate drawings give cost plus a profit margin. Overheads come from the actual cost records, not the tender's preliminaries.

Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.

Қысқаша. Date awareness from the records, notify inside the period, claim time only for delay on the critical path, and add Profit only where the clause gives it.