OpenConstruction Academy
Σύνδεση / Εγγραφή
EL

Θεωρία πριν από την εργασία 2 · 10 λ.

Bill items and measures items (措施项目)

Μετρούμενες εργασίες και παρεπόμενα μέτρα

Μετά από αυτή τη διάλεξη μπορείτε να

  1. Total the bill items (分部分项工程费) as quantity × 综合单价.
  2. Price measures items that do not stay in the building: scaffolding, formwork, work-safety measures.
  3. Take the work-safety measures fee (安全生产措施费) on the base the rules set.
1 / 3

Two kinds of cost in one bill

A Chinese bill of quantities separates work that stays in the building, the 分部分项工程 (bill items: concrete, walls, steel), from the 措施项目, measures needed to build it that leave nothing behind: scaffolding, formwork and supports, temporary works, safety. Bill items are priced quantity × 综合单价. Measures are priced either by quantity (scaffolding per m² of floor area, formwork per m² of contact area) or as a lump item.

Παράδειγμα. Formwork measured by contact area is the area of concrete touching the forms, not the floor area.
2 / 3

Work-safety measures: priced by the rules

The work-safety measures fee (安全生产措施费; the 2013 edition's 安全文明施工费) pays for site safety and the measures that keep the work safe. GB/T 50500-2024 (clause 3.2.5) has it priced by the national, provincial and sector rules, so a bidder takes the regulated rate instead of cutting it to win. The rate and its base come from the provincial rules or the contract; here the base is the total of bill items only.

Παράδειγμα. 2.8 % of bill items of 167,120.40 is 4,679.37.
Bill items total¥167,120.40
Rate2.8%
Work-safety measures fee¥4,679.37
3 / 3

Keep the bases apart

The fee's base is the bill items, not bill items plus measures: a fee taken on a total that already contains it, or contains other measures, inflates itself. Total the bill items first, then the fee, then add it to scaffolding and formwork for the measures total.

Παράδειγμα. Measures = scaffolding + formwork + safety fee.

Total a small bill

Two bill items and three measures.

Όχι υπό κλίμακα
Το πρόβλημα
  • Bill items: slab 120 m³ at ¥671.67; block walls 210 m³ at ¥412.00.
  • Scaffolding ¥36.00 per m² of floor area, 900 m². Formwork ¥48.00 per m² of contact area, 1,050 m².
  • Work-safety measures fee: 2.8 % of the bill items total.
Βήμα 1 από 3

Bill items total

Quantity × rate for both. What is the 分部分项工程费?

120 × ¥671.67 + 210 × ¥412.00 = ¥167,120.40.

Βήμα 2 από 3

Safety fee

2.8 % of the bill items total. What is it?

¥167,120.40 × 2.8 % = ¥4,679.37.

¥32,400¥50,400
  • Scaffolding ¥32,400
  • Formwork ¥50,400
  • Safety fee ¥4,679
¥32,400¥50,400
  • Scaffolding ¥32,400
  • Formwork ¥50,400
  • Safety fee ¥4,679
Βήμα 3 από 3

Measures total

Scaffolding + formwork + safety fee. What is the 措施项目费?

900 × ¥36.00 + 1,050 × ¥48.00 + ¥4,679.37 = ¥87,479.37.

Με λίγα λόγια. Bill items first, then the safety fee on them, then the measures. The safety fee is priced at the regulated rate, never cut.

Ελέγξτε τον εαυτό σας

Ερώτηση 1 από 3

Bill items total 500,000.00 yuan. The work-safety measures fee is 3 % of bill items. What is it?

500,000.00 × 3 % = ¥15,000.00.
Ερώτηση 2 από 3

Why may a bidder not discount the work-safety measures fee?

  • It is a fee, not a tax.

  • Right.

  • It is in the bid, at a fixed rate.

Ερώτηση 3 από 3

Which is a measures item, not a bill item?

  • The concrete stays in the building.

  • Right. It is struck and leaves nothing behind.

  • Steel stays in the building.