The all-in unit rate (综合单价): building it from norm quantities

Συνολική τιμή μονάδας: δοκοί και υποστυλώματα

Εισαγωγή στο μάθημα

Μετά από αυτή τη διάλεξη μπορείτε να

  1. Name the five parts of a 综合单价: labour, materials, machinery, management fee and profit.
  2. Convert tax-inclusive prices to prices net of VAT before building the rate.
  3. Apply management fee and profit to the base the contract names.
1 / 3

What a bill rate in China contains

Chinese public works are priced on a bill of quantities under GB/T 50500, the standard for pricing with bills of quantities (2013 edition, now replaced by GB/T 50500-2024). Each item of the bill carries one 综合单价, an all-in unit rate: labour, materials and machinery used for one unit, plus the enterprise management fee and profit, with the risk the contract places on the contractor. VAT is never in it. The 2024 standard makes the rate the full price before tax (clause 3.1.6) and lists no separate 规费; in this case the workforce's social insurance and housing fund are in the labour rate.

Παράδειγμα. Item codes and measurement rules come from the measurement standard for building works: a cast-in-place beam is measured in m³. GB/T 50854-2024 replaced the 2013 edition on 1 September 2025 and renumbers some items (formwork, scaffolding, rebar); this case keeps the 2013 codes.
2 / 3

Prices net of VAT

Under the general VAT method (一般计税) the contractor's input VAT on materials and machinery is credited against the VAT it charges. So the rate is built on prices net of VAT (除税价): tax-inclusive price ÷ (1 + rate). Materials and machinery hire carry 13 %. Labour carries no input VAT. VAT on the bill, 9 % for construction services, is added at the end.

Παράδειγμα. Ready-mixed concrete at 452.00 yuan per m³ including 13 % VAT is 400.00 yuan net.
Price including VAT¥452.00
VAT 13 % inside it¥52.00
Price net of VAT¥400.00
3 / 3

Norm quantities and the fee base

A consumption norm (定额) gives what one unit consumes: workdays, m³ of concrete including a small loss (1.015 m³ per m³), m² of curing cover, machine shifts (台班). Price each at its net rate. The management fee and profit are percentages of a base fixed by the contract or the provincial fee rules; in this course the base is labour plus machinery, a common choice. Taking them on the whole direct cost instead inflates the rate.

Παράδειγμα. Labour 182.00 and machinery 34.20: a 12 % management fee is 12 % of 216.20, not of the total including concrete.

Price a cast-in-place slab, C25

Norm quantities per m³ of slab. Build the 综合单价.

Όχι υπό κλίμακα
Το πρόβλημα
  • Labour 1.3 workdays at ¥140.00 per workday.
  • Concrete 1.01 m³ at ¥452.00; curing film 2.8 m² at ¥3.39; vibrator 0.45 shifts at ¥13.56; pump 0.02 shifts at ¥2,034.00. All prices include 13 % VAT.
  • Management fee 12 % and profit 7 %, both on labour + machinery.
Βήμα 1 από 3

Materials net of VAT

Concrete and film, each ÷ 1.13. What are the materials per m³?

1.01 × ¥452.00/1.13 + 2.8 × ¥3.39/1.13 = ¥414.40.

Βήμα 2 από 3

Machinery net of VAT

Vibrator and pump. What is the machinery per m³?

0.45 × ¥13.56/1.13 + 0.02 × ¥2,034.00/1.13 = ¥34.20.

¥182¥414
  • Labour ¥182
  • Materials ¥414
  • Machinery ¥34.20
  • Management ¥25.94
  • Profit ¥15.13
¥182¥414
  • Labour ¥182
  • Materials ¥414
  • Machinery ¥34.20
  • Management ¥25.94
  • Profit ¥15.13
Βήμα 3 από 3

综合单价

Labour + materials + machinery + 12 % and 7 % on (labour + machinery). What is the rate?

¥182.00 + ¥414.40 + ¥34.20 + ¥25.94 + ¥15.13 = ¥671.67 per m³.

Με λίγα λόγια. Net prices, norm quantities, fees on the contract's base. The 综合单价 never holds VAT; it is the full price before tax, so no 规费 go on top.

Ελέγξτε τον εαυτό σας

Ερώτηση 1 από 3

A material costs 226.00 yuan including 13 % VAT. What is its price net of VAT?

226.00 ÷ 1.13 = ¥200.00.
Ερώτηση 2 από 3

Which of these is inside a 综合单价?

  • VAT is added on the whole bill, outside the item rates.

  • Right.

  • The provisional sum is its own line under other items, not part of any rate.

Ερώτηση 3 από 3

The contract takes management fee on labour plus machinery. What goes wrong if you take it on the whole direct cost?

  • Materials would carry the fee too.

  • Right.

  • A larger base gives a larger fee.