Πρακτική τιμολόγηση βάσει Πίνακα Ποσοτήτων: GB/T 50500-2024 (Κίνα)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

Έναρξη εργασίας 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Φανταστικό έργο
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
Εργασία στο ERP
5 εργασίες, περίπου 3 ώ. 40 λ.

Ποιος δίνει τι σε ποιον

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Έρχεται σε εσάς

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesΕργασία 1
    • Measures and the safety fee rateΕργασία 2
    • Fee and VAT termsΕργασία 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedΕργασία 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Εργασία 4
    • Re-measured quantitiesΕργασία 5
ΕσείςCost estimator (造价员), contractor

Φεύγει από εσάς

    • The priced bidΕργασία 3
    • Progress payment 1Εργασία 4
    • Rate adjustment for two itemsΕργασία 5
    County Education BureauEmployer, pays

Το έργο και τα πρόσωπα είναι φανταστικά. Τα πορτρέτα είναι παραγόμενα.

Η διαδρομή σας στο έργο

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Εργασία 1 · 45 λ.

    Συνολική τιμή μονάδας: δοκοί και υποστυλώματα

    Παράγετε
    All-in unit rates (综合单价) for beams and columns
    Έγγραφο
    Norm quantities, prices with VAT, fee rates
    Στο ERP
    Bill of Quantities
  2. Bid

    Εργασία 2 · 40 λ.

    Μετρούμενες εργασίες και παρεπόμενα μέτρα

    Παράγετε
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Έγγραφο
    Scaffold and formwork rates, the fee's base
    Στο ERP
    Bill of Quantities
  3. Bid

    Εργασία 3 · 40 λ.

    ΦΠΑ στις τρεις ενότητες

    Παράγετε
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Έγγραφο
    The contract's pricing and tax terms, a colleague's draft
    Στο ERP
    Bill of Quantities › Markups
  4. Payment

    Εργασία 4 · 50 λ.

    Ενδιάμεσος λογαριασμός και συμψηφισμός προκαταβολής

    Παράγετε
    Advance recovery and the amount payable for period 1
    Έγγραφο
    A colleague's draft and the contract terms
    Στο ERP
    Contracts › Progress Claims
  5. Review

    Εργασία 5 · 45 λ.

    Απόκλιση ποσοτήτων άνω του 15 %

    Παράγετε
    Adjusted rates and the variation amount
    Έγγραφο
    Quantities re-measured after completion
    Στο ERP
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Εργασία 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Εργασία 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Εργασία 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Εργασία 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Με μπλε ό,τι προσθέτει η εργασία· με γκρι ό,τι έρχεται από πριν.

Με λίγα λόγια. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.