Introducere în curs · 3 min
Ofertarea pe baza listei de cantități în practică: GB/T 50500-2024 (China)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Proiect fictiv- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Lucru în ERP
- 5 sarcini, circa 3 h 40 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesSarcina 1
- Measures and the safety fee rateSarcina 2
- Fee and VAT termsSarcina 3
- A colleagueDrafted payment 1
- Draft with the bases swappedSarcina 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Sarcina 4
- Re-measured quantitiesSarcina 5
TuCost estimator (造价员), contractorPleacă de la tine
- The priced bidSarcina 3
- Progress payment 1Sarcina 4
- Rate adjustment for two itemsSarcina 5
County Education BureauEmployer, pays
Proiectul și persoanele sunt fictive. Portretele sunt generate.
Traseul tău prin proiect
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Sarcina 1 · 45 min
Preț unitar compus: grinzi și stâlpi
- Produci
- All-in unit rates (综合单价) for beams and columns
- Document
- Norm quantities, prices with VAT, fee rates
- În ERP
- Bill of Quantities
Bid
Sarcina 2 · 40 min
Lucrări măsurate și lucrări auxiliare
- Produci
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Document
- Scaffold and formwork rates, the fee's base
- În ERP
- Bill of Quantities
Bid
Sarcina 3 · 40 min
TVA la cele trei secțiuni
- Produci
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Document
- The contract's pricing and tax terms, a colleague's draft
- În ERP
- Bill of Quantities › Markups
Payment
Sarcina 4 · 50 min
Plata intermediară și recuperarea avansului
- Produci
- Advance recovery and the amount payable for period 1
- Document
- A colleague's draft and the contract terms
- În ERP
- Contracts › Progress Claims
Review
Sarcina 5 · 45 min
Abatere de cantități de peste 15 %
- Produci
- Adjusted rates and the variation amount
- Document
- Quantities re-measured after completion
- În ERP
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.