Introducere în curs · 3 min

Ofertarea pe baza listei de cantități în practică: GB/T 50500-2024 (China)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

Începe sarcina 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Proiect fictiv
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
Lucru în ERP
5 sarcini, circa 3 h 40 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesSarcina 1
    • Measures and the safety fee rateSarcina 2
    • Fee and VAT termsSarcina 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedSarcina 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Sarcina 4
    • Re-measured quantitiesSarcina 5
TuCost estimator (造价员), contractor

Pleacă de la tine

    • The priced bidSarcina 3
    • Progress payment 1Sarcina 4
    • Rate adjustment for two itemsSarcina 5
    County Education BureauEmployer, pays

Proiectul și persoanele sunt fictive. Portretele sunt generate.

Traseul tău prin proiect

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Sarcina 1 · 45 min

    Preț unitar compus: grinzi și stâlpi

    Produci
    All-in unit rates (综合单价) for beams and columns
    Document
    Norm quantities, prices with VAT, fee rates
    În ERP
    Bill of Quantities
  2. Bid

    Sarcina 2 · 40 min

    Lucrări măsurate și lucrări auxiliare

    Produci
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Document
    Scaffold and formwork rates, the fee's base
    În ERP
    Bill of Quantities
  3. Bid

    Sarcina 3 · 40 min

    TVA la cele trei secțiuni

    Produci
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Document
    The contract's pricing and tax terms, a colleague's draft
    În ERP
    Bill of Quantities › Markups
  4. Payment

    Sarcina 4 · 50 min

    Plata intermediară și recuperarea avansului

    Produci
    Advance recovery and the amount payable for period 1
    Document
    A colleague's draft and the contract terms
    În ERP
    Contracts › Progress Claims
  5. Review

    Sarcina 5 · 45 min

    Abatere de cantități de peste 15 %

    Produci
    Adjusted rates and the variation amount
    Document
    Quantities re-measured after completion
    În ERP
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Sarcina 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Sarcina 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Sarcina 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Sarcina 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.