Introduktion till kursen · 3 min
Prissättning efter mängdförteckning i praktiken: GB/T 50500-2024 (Kina)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Fiktivt projekt- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Arbete i ERP
- 5 uppgifter, cirka 3 h 40 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesUppgift 1
- Measures and the safety fee rateUppgift 2
- Fee and VAT termsUppgift 3
- A colleagueDrafted payment 1
- Draft with the bases swappedUppgift 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Uppgift 4
- Re-measured quantitiesUppgift 5
DuCost estimator (造价员), contractorGår från dig
- The priced bidUppgift 3
- Progress payment 1Uppgift 4
- Rate adjustment for two itemsUppgift 5
County Education BureauEmployer, pays
Projektet och personerna är fiktiva. Porträtten är genererade.
Din väg genom projektet
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Uppgift 1 · 45 min
Sammansatt à-pris: balkar och pelare
- Du tar fram
- All-in unit rates (综合单价) for beams and columns
- Dokument
- Norm quantities, prices with VAT, fee rates
- I ERP
- Bill of Quantities
Bid
Uppgift 2 · 40 min
Mätta arbeten och åtgärdsposter
- Du tar fram
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Dokument
- Scaffold and formwork rates, the fee's base
- I ERP
- Bill of Quantities
Bid
Uppgift 3 · 40 min
Moms på de tre delarna
- Du tar fram
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Dokument
- The contract's pricing and tax terms, a colleague's draft
- I ERP
- Bill of Quantities › Markups
Payment
Uppgift 4 · 50 min
Delbetalning och förskottsavräkning
- Du tar fram
- Advance recovery and the amount payable for period 1
- Dokument
- A colleague's draft and the contract terms
- I ERP
- Contracts › Progress Claims
Review
Uppgift 5 · 45 min
Mängdavvikelse över 15 %
- Du tar fram
- Adjusted rates and the variation amount
- Dokument
- Quantities re-measured after completion
- I ERP
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.