Prissättning efter mängdförteckning i praktiken: GB/T 50500-2024 (Kina)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

Starta uppgift 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Fiktivt projekt
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
Arbete i ERP
5 uppgifter, cirka 3 h 40 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesUppgift 1
    • Measures and the safety fee rateUppgift 2
    • Fee and VAT termsUppgift 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedUppgift 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Uppgift 4
    • Re-measured quantitiesUppgift 5
DuCost estimator (造价员), contractor

Går från dig

    • The priced bidUppgift 3
    • Progress payment 1Uppgift 4
    • Rate adjustment for two itemsUppgift 5
    County Education BureauEmployer, pays

Projektet och personerna är fiktiva. Porträtten är genererade.

Din väg genom projektet

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Uppgift 1 · 45 min

    Sammansatt à-pris: balkar och pelare

    Du tar fram
    All-in unit rates (综合单价) for beams and columns
    Dokument
    Norm quantities, prices with VAT, fee rates
    I ERP
    Bill of Quantities
  2. Bid

    Uppgift 2 · 40 min

    Mätta arbeten och åtgärdsposter

    Du tar fram
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Dokument
    Scaffold and formwork rates, the fee's base
    I ERP
    Bill of Quantities
  3. Bid

    Uppgift 3 · 40 min

    Moms på de tre delarna

    Du tar fram
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Dokument
    The contract's pricing and tax terms, a colleague's draft
    I ERP
    Bill of Quantities › Markups
  4. Payment

    Uppgift 4 · 50 min

    Delbetalning och förskottsavräkning

    Du tar fram
    Advance recovery and the amount payable for period 1
    Dokument
    A colleague's draft and the contract terms
    I ERP
    Contracts › Progress Claims
  5. Review

    Uppgift 5 · 45 min

    Mängdavvikelse över 15 %

    Du tar fram
    Adjusted rates and the variation amount
    Dokument
    Quantities re-measured after completion
    I ERP
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Uppgift 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Uppgift 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Uppgift 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Uppgift 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.