معرفی دوره · 3 دقیقه

قیمت‌گذاری عملی بر پایه صورت مقادیر: GB/T 50500-2024 (چین)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

شروع تکلیف 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.پروژهٔ خیالی
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
کار در ERP
5 تکلیف، حدود 3 ساعت 40 دقیقه

چه کسی چه چیزی به چه کسی می‌دهد

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

به شما می‌رسد

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesتکلیف 1
    • Measures and the safety fee rateتکلیف 2
    • Fee and VAT termsتکلیف 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedتکلیف 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1تکلیف 4
    • Re-measured quantitiesتکلیف 5
شماCost estimator (造价员), contractor

از شما می‌رود

    • The priced bidتکلیف 3
    • Progress payment 1تکلیف 4
    • Rate adjustment for two itemsتکلیف 5
    County Education BureauEmployer, pays

پروژه و افراد خیالی‌اند. چهره‌ها ساختگی هستند.

مسیر شما در پروژه

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    تکلیف 1 · 45 دقیقه

    نرخ واحد جامع: تیر و ستون

    خروجی شما
    All-in unit rates (综合单价) for beams and columns
    سند
    Norm quantities, prices with VAT, fee rates
    در ERP
    Bill of Quantities
  2. Bid

    تکلیف 2 · 40 دقیقه

    کارهای اندازه‌گیری‌شده و اقدامات جانبی

    خروجی شما
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    سند
    Scaffold and formwork rates, the fee's base
    در ERP
    Bill of Quantities
  3. Bid

    تکلیف 3 · 40 دقیقه

    مالیات بر ارزش افزوده روی سه بخش

    خروجی شما
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    سند
    The contract's pricing and tax terms, a colleague's draft
    در ERP
    Bill of Quantities › Markups
  4. Payment

    تکلیف 4 · 50 دقیقه

    صورت‌وضعیت موقت و کسر پیش‌پرداخت

    خروجی شما
    Advance recovery and the amount payable for period 1
    سند
    A colleague's draft and the contract terms
    در ERP
    Contracts › Progress Claims
  5. Review

    تکلیف 5 · 45 دقیقه

    انحراف مقدار بیش از 15 %

    خروجی شما
    Adjusted rates and the variation amount
    سند
    Quantities re-measured after completion
    در ERP
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
تکلیف 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
تکلیف 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
تکلیف 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
تکلیف 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

آبی چیزی است که تکلیف اضافه می‌کند؛ خاکستری از مرحلهٔ قبل آمده است.

به‌طور خلاصه. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.