Курска киришүү · 3 мүн
Көлөмдөр тизмеси боюнча баа коюу практикада: GB/T 50500-2024 (Кытай)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Ойдон чыгарылган долбоор- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- ERPдеги иш
- Тапшырмалар: 5, болжол менен 3 саат 40 мүн
Ким кимге эмне берет
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- Tender documentsBill, norms, contract terms
- Norm quantities and prices1-тапшырма
- Measures and the safety fee rate2-тапшырма
- Fee and VAT terms3-тапшырма
- A colleagueDrafted payment 1
- Draft with the bases swapped4-тапшырма
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 14-тапшырма
- Re-measured quantities5-тапшырма
СизCost estimator (造价员), contractorСизден кетет
- The priced bid3-тапшырма
- Progress payment 14-тапшырма
- Rate adjustment for two items5-тапшырма
County Education BureauEmployer, pays
Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.
Долбоор боюнча жолуңуз
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
1-тапшырма · 45 мүн
Комплекстүү бирдик баа: балкалар жана колонналар
- Натыйжа
- All-in unit rates (综合单价) for beams and columns
- Документ
- Norm quantities, prices with VAT, fee rates
- ERPде
- Bill of Quantities
Bid
2-тапшырма · 40 мүн
Өлчөнгөн иштер жана чаралык иштер
- Натыйжа
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Документ
- Scaffold and formwork rates, the fee's base
- ERPде
- Bill of Quantities
Bid
3-тапшырма · 40 мүн
Үч бөлүккө КНС
- Натыйжа
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Документ
- The contract's pricing and tax terms, a colleague's draft
- ERPде
- Bill of Quantities › Markups
Payment
4-тапшырма · 50 мүн
Аралык төлөм жана алдын ала төлөмдү кармап калуу
- Натыйжа
- Advance recovery and the amount payable for period 1
- Документ
- A colleague's draft and the contract terms
- ERPде
- Contracts › Progress Claims
Review
5-тапшырма · 45 мүн
15 %дан ашык көлөмдүн четтөөсү
- Натыйжа
- Adjusted rates and the variation amount
- Документ
- Quantities re-measured after completion
- ERPде
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.