OpenConstruction Academy
Кирүү / Катталуу
KY

Курска киришүү · 3 мүн

Көлөмдөр тизмеси боюнча баа коюу практикада: GB/T 50500-2024 (Кытай)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

1-тапшырманы баштоо

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Ойдон чыгарылган долбоор
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
ERPдеги иш
Тапшырмалар: 5, болжол менен 3 саат 40 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • Tender documentsBill, norms, contract terms
    • Norm quantities and prices1-тапшырма
    • Measures and the safety fee rate2-тапшырма
    • Fee and VAT terms3-тапшырма
  • A colleagueDrafted payment 1
    • Draft with the bases swapped4-тапшырма
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 14-тапшырма
    • Re-measured quantities5-тапшырма
СизCost estimator (造价员), contractor

Сизден кетет

    • The priced bid3-тапшырма
    • Progress payment 14-тапшырма
    • Rate adjustment for two items5-тапшырма
    County Education BureauEmployer, pays

Долбоор жана адамдар ойдон чыгарылган. Портреттер генерацияланган.

Долбоор боюнча жолуңуз

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    1-тапшырма · 45 мүн

    Комплекстүү бирдик баа: балкалар жана колонналар

    Натыйжа
    All-in unit rates (综合单价) for beams and columns
    Документ
    Norm quantities, prices with VAT, fee rates
    ERPде
    Bill of Quantities
  2. Bid

    2-тапшырма · 40 мүн

    Өлчөнгөн иштер жана чаралык иштер

    Натыйжа
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Документ
    Scaffold and formwork rates, the fee's base
    ERPде
    Bill of Quantities
  3. Bid

    3-тапшырма · 40 мүн

    Үч бөлүккө КНС

    Натыйжа
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Документ
    The contract's pricing and tax terms, a colleague's draft
    ERPде
    Bill of Quantities › Markups
  4. Payment

    4-тапшырма · 50 мүн

    Аралык төлөм жана алдын ала төлөмдү кармап калуу

    Натыйжа
    Advance recovery and the amount payable for period 1
    Документ
    A colleague's draft and the contract terms
    ERPде
    Contracts › Progress Claims
  5. Review

    5-тапшырма · 45 мүн

    15 %дан ашык көлөмдүн четтөөсү

    Натыйжа
    Adjusted rates and the variation amount
    Документ
    Quantities re-measured after completion
    ERPде
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
1-тапшырмаAll-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
2-тапшырмаMeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
3-тапшырмаVATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
4-тапшырмаPaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.